Skip to main content

CPWD Analysis of Rates · New Technologies and Materials

Drilling suitable holes in reinforced or plain cement concrete with power driven drill machine to a minimum depth of 100mm upto 200mm in RCC beams, lintels, columns and slabs to introduce steel bars for sunshades/balconies including fixing the steel bars in position using epoxy resin anchor grout of approved make but excluding the cost of reinforcement, all complete as per direction of Engineer-In-Charge

Upto and including 12mm dia

Item number
26.30.1
Analysis basis
Details of cost for 10 holes
Priced inputs
4
Derived rate
141.20 / holes

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.30.1 Drilling suitable holes in reinforced or plain cement concrete with power driven drill machine to a minimum depth of 100mm upto 200mm in RCC beams, lintels, columns and slabs to introduce steel bars for sunshades/balconies including fixing the steel bars in position using epoxy resin anchor grout of approved make but excluding the cost of reinforcement, all complete as per direction of Engineer-In-Charge Upto and including 12mm dia — is derived from 4 priced inputs for 10 holes and works out to ₹141.20 per holes after water charges, GST, CPOH and cess. The full build-up is below.

  • Approx unit Weight of Epoxy= 2000kg/cum
  • or 2gm/cucm
  • Volume of Epoxy filled =3.14/4[(1.5)2-(1.2)2]
  • x 15.5cm = 9.86cucm
  • Weight of Epoxy for 10 holes=10x9.86 x 2 =
  • 197.20 gms say 200gms = 0.2 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
7913EpoxyMaterialkg0.2380.0076.00
0088Hire charges of Drill machine upto 30 mm diaMachineryday0.5200.00100.00
0116Fitter (grade 1)Labourday0.5897.00448.50
0114BeldarLabourday0.5736.00368.00
TOTAL
992.50
Add 1 % Water charges on “W”
9.93
TOTAL
1,002.43
Add GST on “X” (multiplying factor 0.2127)
213.22
TOTAL
1,215.65
Add 15% CPOH on “Y”
182.35
TOTAL
1,398.00
Add Cess @ 1% on “Z”
13.98
Rate for 10 holes
1,411.98
Rate for one hole
141.20
Say
141.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1949. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works