Drilling suitable holes in reinforced or plain cement concrete with power driven drill machine to a minimum depth of 100mm upto 200mm in RCC beams, lintels, columns and slabs to introduce steel bars for sunshades/balconies including fixing the steel bars in position using epoxy resin anchor grout of approved make but excluding the cost of reinforcement, all complete as per direction of Engineer-In-Charge

Upto and including 12mm dia
Item number
26.30.1
Analysis basis
10 holes
Priced inputs
4
Derived rate
₹141.20/ HOLES
D-01/RATE ANALYSISITEM 26.30.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.30.1 (Drilling suitable holes in reinforced or plain cement concrete with power driven drill machine to a minimum depth of 100mm upto 200mm in RCC beams, lintels, columns and slabs to introduce steel bars for sunshades/balconies including fixing the steel bars in position using epoxy resin anchor grout of approved make but excluding the cost of reinforcement, all complete as per direction of Engineer-In-Charge Upto and including 12mm dia) is derived from 4 priced inputs for 10 holes and works out to ₹141.20 per holes after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Approx unit Weight of Epoxy= 2000kg/cum
  • or 2gm/cucm
  • Volume of Epoxy filled =3.14/4[(1.5)2-(1.2)2]
  • x 15.5cm = 9.86cucm
  • Weight of Epoxy for 10 holes=10x9.86 x 2 =
  • 197.20 gms say 200gms = 0.2 kg
ANALYSIS OF RATES · ITEM 26.30.1DETAILS OF COST FOR 10 HOLES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7913MATEpoxykg0.2380.0076.00
0088MACHHire charges of Drill machine upto 30 mm diaday0.5200.00100.00
0116LABFitter (grade 1)day0.5897.00448.50
0114LABBeldarday0.5736.00368.00
BUILD-UP TO RATE
TOTAL
992.50
Add 1 % Water charges on “W”
+9.93
TOTAL
1,002.43
Add GST on “X” (multiplying factor 0.2127)
+213.22
TOTAL
1,215.65
Add 15% CPOH on “Y”
+182.35
TOTAL
1,398.00
Add Cess @ 1% on “Z”
+13.98
Rate for 10 holes
+1,411.98
Rate for one hole
+141.20
SAY
₹141.20
D-02/SOURCEPRINTED PAGE 1949
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1949

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1949. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.