Skip to main content

CPWD Analysis of Rates · New Technologies and Materials

Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust free steel surface by using alkaline chemical rust remover of approved make with paint brush and removing loose particles after 24 hours of its application with wire brush and thoroughly washing with water and allowing it to dry, all complete as per direction of Engineer-In-Charge

Bars above 12 mm diameter

Item number
26.29.2
Analysis basis
Detail of cost for 3.00 sqm (47.78 metre
Priced inputs
5
Derived rate
16.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.29.2 Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust free steel surface by using alkaline chemical rust remover of approved make with paint brush and removing loose particles after 24 hours of its application with wire brush and thoroughly washing with water and allowing it to dry, all complete as per direction of Engineer-In-Charge Bars above 12 mm diameter — is derived from 5 priced inputs for 3.00 sqm and works out to ₹16.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • length of 20 mm dia bar) Bars above 12 mm
  • diameter
  • (1 litre chemical shall cover 3.00 sqm area
  • of bars)
  • (Application charges for 3.0 sqm)
CodeInputUnitQuantityRate (INR)Amount (INR)
7911Chemical Rust RemoverMateriallitre1290.00290.00
0131PainterLabourday0.162816.00132.19
0115CoolieLabourday0.162736.00119.23
9999Putty, brush, sand paperMaterialL.S.3.1622.277.18
9999SundriesMaterialL.S.1.982.274.49
TOTAL
553.09
Add 1 % Water charges on “W”
5.53
TOTAL
558.62
Add GST on “X” (multiplying factor 0.2127)
118.82
TOTAL
677.44
Add 15% CPOH on “Y”
101.62
TOTAL
779.06
Add Cess @ 1% on “Z”
7.79
Cost of 3.00 sqm (47.78m length of 20 mm dia bar)
786.85
Rate per metre length of bar
16.47
Say
16.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1948. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works