CPWD Analysis of Rates · New Technologies and Materials
Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust free steel surface by using alkaline chemical rust remover of approved make with paint brush and removing loose particles after 24 hours of its application with wire brush and thoroughly washing with water and allowing it to dry, all complete as per direction of Engineer-In-Charge
Bars upto 12 mm diameter
- Item number
- 26.29.1
- Analysis basis
- Detail of cost for 3.00 sqm (95.54 meter
- Priced inputs
- 5
- Derived rate
- ₹8.25 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.29.1 — Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust free steel surface by using alkaline chemical rust remover of approved make with paint brush and removing loose particles after 24 hours of its application with wire brush and thoroughly washing with water and allowing it to dry, all complete as per direction of Engineer-In-Charge Bars upto 12 mm diameter — is derived from 5 priced inputs for 3.00 sqm and works out to ₹8.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- length of 10 mm dia bar) Bars upto 12 mm
- diameter
- (1 litre chemical shall cover 3.00 sqm area
- of bars)
- (Application charges for 3.0 sqm)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7911 | Chemical Rust RemoverMaterial | litre | 1 | 290.00 | 290.00 |
| 0131 | PainterLabour | day | 0.162 | 816.00 | 132.19 |
| 0115 | CoolieLabour | day | 0.162 | 736.00 | 119.23 |
| 9999 | Putty, brush, sand paperMaterial | L.S. | 3.162 | 2.27 | 7.18 |
| 9999 | SundriesMaterial | L.S. | 1.98 | 2.27 | 4.49 |
- TOTAL
- 553.09
- Add 1 % Water charges on “W”
- 5.53
- TOTAL
- 558.62
- Add GST on “X” (multiplying factor 0.2127)
- 118.82
- TOTAL
- 677.44
- Add 15% CPOH on “Y”
- 101.62
- TOTAL
- 779.06
- Add Cess @ 1% on “Z”
- 7.79
- Cost of 3 sqm (95.54 m length of 10 mm dia bar)
- 786.85
- Rate per metre length of bar
- 8.24
- Say
- 8.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1948. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works