Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge

25 mm average thickness
Item number
26.28.3
Analysis basis
One Sqm
Priced inputs
3
Derived rate
₹126.75/ SQM
D-01/RATE ANALYSISITEM 26.28.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.28.3 (Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge 25 mm average thickness) is derived from 3 priced inputs for One Sqm and works out to ₹126.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 25mm average thickness for beams
ANALYSIS OF RATES · ITEM 26.28.3DETAILS OF COST FOR ONE SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATHire charges for HILTY-TE 504 Pneumatic ChiselL.S.1.872.274.24
0157LABMachine OperatorOperator (Pile/ Special machine)day0.07897.0062.79
0114LABBeldarday0.03736.0022.08
BUILD-UP TO RATE
TOTAL
89.11
Add 1 % Water charges on “W”
+0.89
TOTAL
90.00
Add GST on “X” (multiplying factor 0.2127)
+19.14
TOTAL
109.14
Add 15% CPOH on “Y”
+16.37
TOTAL
125.51
Add Cess @ 1% on “Z”
+1.26
Cost of 1.0 sqm
126.77
SAY
₹126.75
D-02/SOURCEPRINTED PAGE 1947
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1947

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1947. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.