CPWD Analysis of Rates · New Technologies and Materials
Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge
50mm average thickness
- Item number
- 26.28.2
- Analysis basis
- Details of cost for One Sqm
- Priced inputs
- 3
- Derived rate
- ₹256.35 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.28.2 — Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge 50mm average thickness — is derived from 3 priced inputs for One Sqm and works out to ₹256.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 50mm average thickness for beams
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 9999 | Hire charges for HILTY-TE 504 Pneumatic ChiselMaterial | L.S. | 3.74 | 2.27 | 8.49 |
| 0157 | Machine OperatorOperator (Pile/ Special machine)Labour | day | 0.134 | 897.00 | 120.20 |
| 0114 | BeldarLabour | day | 0.07 | 736.00 | 51.52 |
- TOTAL
- 180.21
- Add 1 % Water charges on “W”
- 1.80
- TOTAL
- 182.01
- Add GST on “X” (multiplying factor 0.2127)
- 38.71
- TOTAL
- 220.72
- Add 15% CPOH on “Y”
- 33.11
- TOTAL
- 253.83
- Add Cess @ 1% on “Z”
- 2.54
- Cost of 1.0 sqm
- 256.37
- Say
- 256.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1947. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.