Providing & fixing in position Phenol bonded Bamboowood wall cladding at all height with planks of sizes 10mm thick, minimum 1800mm length and minimum 100 mm wide, in approved colour, texture and finish, having Performance Appraisal Certificate (PAC) issued by Building Materials & Technology Promotion Council (BMTPC), with necesasary profiled edges fixed with 40mm SS screws 5 nos in each tile to frame work made of second class teak wood of size 20x15 mm in centre of each tile and bottom and top of work height, 40x15mm placed at ends of each tile. The cladding shall be laid over backlayment of 1.00 mm thick expanded polyethylene foam of density 40kg/cum in two layers, first layer on wall surface before fixing wooden frame and second layer on frame under cladding. The bamboowood planks shall have minimum density of 1000 Kg/cum & minimum Hardness 1000 Kgf. with Eco friendly UV coating, all complete as per direction of the Engineer in-charge

Item number
26.3
Analysis basis
10m x
Priced inputs
11
Derived rate
₹6,283.85/ SQM
D-01/RATE ANALYSISITEM 26.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.3 (Providing & fixing in position Phenol bonded Bamboowood wall cladding at all height with planks of sizes 10mm thick, minimum 1800mm length and minimum 100 mm wide, in approved colour, texture and finish, having Performance Appraisal Certificate (PAC) issued by Building Materials & Technology Promotion Council (BMTPC), with necesasary profiled edges fixed with 40mm SS screws 5 nos in each tile to frame work made of second class teak wood of size 20x15 mm in centre of each tile and bottom and top of work height, 40x15mm placed at ends of each tile. The cladding shall be laid over backlayment of 1.00 mm thick expanded polyethylene foam of density 40kg/cum in two layers, first layer on wall surface before fixing wooden frame and second layer on frame under cladding. The bamboowood planks shall have minimum density of 1000 Kg/cum & minimum Hardness 1000 Kgf. with Eco friendly UV coating, all complete as per direction of the Engineer in-charge) is derived from 11 priced inputs for 10m x and works out to ₹6,283.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 10 x 9.5 = 95 + 9.5 (Add for wastage
  • @10%) = 104.5 sqm
  • At end joints of planks = 4x9.91 = 39.64 mtr
  • + 1.98 (Add for wastage 5%) = 41.62 mtr
  • At perriferi of cladding = 2x(10+9.5)+1.95
  • (Add for wastage @5%) =40.95 metre
  • (2x10x9.5) = 190 + 9.5 (Add for wastage
  • @5%)=199.5 sqm
  • @500mm c/c at teak wood frame
  • (5nos in each panels)
  • No of panels=95/(1.9 x 0.135)=370 nos
  • No. of screws= 370 x 5=1850 nos
  • 10 metre height, at every 1.9 metre height one length of 10 metre i.e
  • (5x9.91x0.02x 0.015+2x10x0.02x.015+2x9.50x.02x.015+4x9.91x0.04x0.015)+wastage @5% =0.05287 cum= 52.87 cudm
ANALYSIS OF RATES · ITEM 26.3DETAILS OF COST FOR 10M X 9.5M = 95 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8025MATBamboo wood Tile Wall Cladding 10mm thick, minimum 1800 mm length and minimum 100 mm wideBamboo wood Tile Wall Cladding 10 mm thick, minimum 1800 mm length and minimum 100 mm widesqm104.53,562.503,72,281.25
8026MATBamboo wood T-mold 14mm thick of size 1900mm x 44mmBamboo wood T-mold 14 mm thick of size 1900 mm x 44 mmmetre41.62275.5011,466.31
8027MATBamboo wood Threshold 14mm thick of size 1900mm x 44mmBamboo wood Threshold 14 mm thick of size 1900 mm x 44 mmmetre40.95275.5011,281.73
8016MATHigh Density expanded poly ethylene (EPE) Foam 1mm thickHigh Density expanded poly ethylene (EPE) Foam 1 mm thicksqm199.512.002,394.00
8210MATStainless steel screws 50 mm100 Nos2.58320.00825.60
8212MATStainless steel screws 30 mm100 Nos18.5255.004,717.50
1190MATSecond class teak wood in planks10 cudm5.287791.004,182.02
0111LABCarpenter 1st classday5897.004,485.00
0112LABCarpenter 2nd classday5816.004,080.00
0114LABBeldarday5736.003,680.00
9999MATSundriesL.S.1002.27227.00
BUILD-UP TO RATE
TOTAL
4,19,620.41
Add 1 % Water charges on “W”
+4,196.20
TOTAL
4,23,816.61
Add GST on “X” (multiplying factor 0.2127)
+90,145.79
TOTAL
5,13,962.40
Add 15% CPOH on “Y”
+77,094.36
TOTAL
5,91,056.76
Add Cess @ 1% on “Z”
+5,910.57
Cost of 95 sqm
5,96,967.33
Cost of 1 sqm
6,283.87
SAY
₹6,283.85
D-02/SOURCEPRINTED PAGE 1908
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1908

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1908. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.