Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORTH SPECIFICATION for base/sub-base reinforcement having minimum tensile strength 15kN/m in the longitudinal and transverse direction, with 5kN/m and 7kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening

Item number
26.12
Analysis basis
300 Sqm
Priced inputs
4
Derived rate
₹249.90/ SQM
D-01/RATE ANALYSISITEM 26.12

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.12 (Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORTH SPECIFICATION for base/sub-base reinforcement having minimum tensile strength 15kN/m in the longitudinal and transverse direction, with 5kN/m and 7kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening) is derived from 4 priced inputs for 300 Sqm and works out to ₹249.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • elements (synthetic geogrids) for wastage
  • and accessories like tie-strips, nuts and
  • bolts and loops/lugs for joining reinforcing
  • elements with the facia pannels, overlaps
  • and other protective elements for synthetic
  • geogrids and all other activities required to
  • complete the item in all respect including
  • Add 10 per cent of the cost of reinforcing
ANALYSIS OF RATES · ITEM 26.12DETAILS OF COST FOR 300 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8956MATBi-Axial Extruded GeoGrids of Minimum Tensile Strength 15 kN/m in the longitudinal and transverse directionBi-Axial Extruded Geogrids of Minimum Tensile Strength 15 kN/m in the longitudinal and transverse directionSqm300138.0041,400.00
0128LABMateday0.36816.00293.76
0114LABBeldarday6736.004,416.00
0139LABSkilled BeldarSkilled Beldar (for floor rubbing etc.)day3816.002,448.00
BUILD-UP TO RATE
taxes and transportation. 10% of “P”
+4,140.00
TOTAL
52,697.76
Add 1 % Water charges on “W”
+526.98
TOTAL
53,224.74
Add GST on “X” (multiplying factor 0.2127)
+11,320.90
TOTAL
64,545.64
Add 15% CPOH on “Y”
+9,681.85
TOTAL
74,227.49
Add Cess @ 1% on “Z”
+742.27
Cost for 300 Sqm
74,969.76
Cost per Sqm
249.90
SAY
₹249.90
D-02/SOURCEPRINTED PAGE 1921
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1921

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1921. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.