Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORTH SPECIFICATION for base/sub-base reinforcement having minimum tensile strength 15kN/m in the longitudinal and transverse direction, with 5kN/m and 7kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening
- Item number
- 26.12
- Analysis basis
- 300 Sqm
- Priced inputs
- 4
- Derived rate
- ₹249.90/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.12 (Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORTH SPECIFICATION for base/sub-base reinforcement having minimum tensile strength 15kN/m in the longitudinal and transverse direction, with 5kN/m and 7kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening) is derived from 4 priced inputs for 300 Sqm and works out to ₹249.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- elements (synthetic geogrids) for wastage
- and accessories like tie-strips, nuts and
- bolts and loops/lugs for joining reinforcing
- elements with the facia pannels, overlaps
- and other protective elements for synthetic
- geogrids and all other activities required to
- complete the item in all respect including
- Add 10 per cent of the cost of reinforcing
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8956 | MAT | Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 15 kN/m in the longitudinal and transverse directionBi-Axial Extruded Geogrids of Minimum Tensile Strength 15 kN/m in the longitudinal and transverse direction | Sqm | 300 | 138.00 | 41,400.00 |
| 0128 | LAB | Mate | day | 0.36 | 816.00 | 293.76 |
| 0114 | LAB | Beldar | day | 6 | 736.00 | 4,416.00 |
| 0139 | LAB | Skilled BeldarSkilled Beldar (for floor rubbing etc.) | day | 3 | 816.00 | 2,448.00 |
- taxes and transportation. 10% of “P”
- +4,140.00
- TOTAL
- 52,697.76
- Add 1 % Water charges on “W”
- +526.98
- TOTAL
- 53,224.74
- Add GST on “X” (multiplying factor 0.2127)
- +11,320.90
- TOTAL
- 64,545.64
- Add 15% CPOH on “Y”
- +9,681.85
- TOTAL
- 74,227.49
- Add Cess @ 1% on “Z”
- +742.27
- Cost for 300 Sqm
- 74,969.76
- Cost per Sqm
- 249.90
- SAY
- ₹249.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1921
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1921. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.