Skip to main content

Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORTH SPECIFICATION for base/sub-base reinforcement having minimum tensile strength 20kN/m in the longitudinal and transverse direction, with 7kN/m and 14kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening

Item number
26.13
Analysis basis
300 Sqm
Priced inputs
4
Derived rate
₹276.50/ SQM
D-01/RATE ANALYSISITEM 26.13

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.13 (Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORTH SPECIFICATION for base/sub-base reinforcement having minimum tensile strength 20kN/m in the longitudinal and transverse direction, with 7kN/m and 14kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening) is derived from 4 priced inputs for 300 Sqm and works out to ₹276.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • elements (synthetic geogrids) for wastage
  • and accessories like tie-strips, nuts and
  • bolts and loops/lugs for joining reinforcing
  • elements with the facia pannels, overlaps
  • and other protective elements for synthetic
  • geogrids and all other activities required to
  • complete the item in all respect including
  • Add 10 per cent of the cost of reinforcing
ANALYSIS OF RATES · ITEM 26.13DETAILS OF COST FOR 300 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8957MATBi-Axial Extruded GeoGrids of Minimum Tensile Strength 20kN/m in the longitudinal and transverse directionBi-Axial Extruded Geogrids of Minimum Tensile Strength 20kN/m in the longitudinal and transverse directionsqm300155.0046,500.00
0128LABMateday0.36816.00293.76
0114LABBeldarday6736.004,416.00
0139LABSkilled BeldarSkilled Beldar (for floor rubbing etc.)day3816.002,448.00
BUILD-UP TO RATE
taxes and transportation. 10% of “P”
+4,650.00
TOTAL
58,307.76
Add 1 % Water charges on “W”
+583.08
TOTAL
58,890.84
Add GST on “X” (multiplying factor 0.2127)
+12,526.08
TOTAL
71,416.92
Add 15% CPOH on “Y”
+10,712.54
TOTAL
82,129.46
Add Cess @ 1% on “Z”
+821.29
Cost for 300 Sqm
82,950.75
Cost per Sqm
276.50
SAY
₹276.50
D-02/SOURCEPRINTED PAGE 1922
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1922

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1922. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSNEW TECHNOLOGIES AND MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.