Skip to main content

CPWD Analysis of Rates · New Technologies and Materials

Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORTH SPECIFICATION for base/sub-base reinforcement having minimum tensile strength 20kN/m in the longitudinal and transverse direction, with 7kN/m and 14kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening

Item number
26.13
Analysis basis
Details of Cost for 300 Sqm
Priced inputs
4
Derived rate
276.50 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 26.13 Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORTH SPECIFICATION for base/sub-base reinforcement having minimum tensile strength 20kN/m in the longitudinal and transverse direction, with 7kN/m and 14kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening — is derived from 4 priced inputs for 300 Sqm and works out to ₹276.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • elements (synthetic geogrids) for wastage
  • and accessories like tie-strips, nuts and
  • bolts and loops/lugs for joining reinforcing
  • elements with the facia pannels, overlaps
  • and other protective elements for synthetic
  • geogrids and all other activities required to
  • complete the item in all respect including
  • Add 10 per cent of the cost of reinforcing
CodeInputUnitQuantityRate (INR)Amount (INR)
8957Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 20kN/m in the longitudinal and transverse directionBi-Axial Extruded Geogrids of Minimum Tensile Strength 20kN/m in the longitudinal and transverse directionMaterialsqm300155.0046,500.00
0128MateLabourday0.36816.00293.76
0114BeldarLabourday6736.004,416.00
0139Skilled BeldarSkilled Beldar (for floor rubbing etc.)Labourday3816.002,448.00
taxes and transportation. 10% of “P”
4,650.00
TOTAL
58,307.76
Add 1 % Water charges on “W”
583.08
TOTAL
58,890.84
Add GST on “X” (multiplying factor 0.2127)
12,526.08
TOTAL
71,416.92
Add 15% CPOH on “Y”
10,712.54
TOTAL
82,129.46
Add Cess @ 1% on “Z”
821.29
Cost for 300 Sqm
82,950.75
Cost per Sqm
276.50
Say
276.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1922. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works