CPWD Analysis of Rates · Masonry Work

Brick work in plain arches in superstructure above plinth level and upto floor five level including centering and shuttering complete for span up to 6 metres with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in cement mortar 1:3 (1 cement : 3 coarse sand)

Item number
6.9
Analysis basis
Details of cost for 1 cum.
Priced inputs
10
Derived rate
15,077.95 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.9 Brick work in plain arches in superstructure above plinth level and upto floor five level including centering and shuttering complete for span up to 6 metres with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in cement mortar 1:3 (1 cement : 3 coarse sand) — is derived from 10 priced inputs for 1 cum and works out to ₹15,077.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1:3
  • Centring and shuttering
  • Taking a semi circular arch 3.6m span,
  • 3.6m long and 0.40m thick
  • Area of centering = 3.142 x 1.8 x 3.6 =
  • 20.37 sqm.
  • Brick work in Arch = 3.142x2.00x0.4x3.6 =
  • 9.05cum.
  • Area per cum = 20.37/9.05 = 2.25 sqm
  • Extra labour for lifting of material (above
  • floor two level up to floor five level)
CodeInputUnitQuantityRate (INR)Amount (INR)
2602Common burnt clay F.P.S. (non modular) bricks class designation 7.5Material1000 Nos0.4944,724.002,333.66
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.254,881.951,220.49
9999SundriesMaterialL.S.2.732.276.20
Rate as per item no 5.9.9 of SH : Reinforced cement concrete workRate as per item 5.9.9Sub-analysissqm2.252,154.354,847.29
9999ScaffoldingMaterialL.S.18.852.2742.79
0123Mason 1st classMason 1st classLabourday0.53897.00475.41
0124Mason 2nd classMason 2nd classLabourday0.53816.00432.48
0115CoolieLabourday2.29736.001,685.44
0101BhistiLabourday0.2816.00163.20
0115CoolieLabourday1.13736.00831.68
TOTAL
12,038.64
Add 1 % Water charges on “W-A”
71.91
TOTAL
12,110.55
Add GST on “X-A” (multiplying factor 0.2127)
1,544.90
TOTAL
13,655.45
Add 15% CPOH on “Y-A”
1,321.22
TOTAL
14,976.67
Add Cess @ 1% on “Z-A”
101.29
Cost for 1 cum.
15,077.96
Say
15,077.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 313. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works