Brick work in gauged arches in superstructure above plinth level and upto floor five level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering and shuttering complete, for span up to 6 meters with common burnt clay F.P.S. (non modular) bricks of class designation 7.5
- Item number
- 6.10
- Analysis basis
- 1 cum
- Priced inputs
- 10
- Derived rate
- ₹19,066.10/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.10 (Brick work in gauged arches in superstructure above plinth level and upto floor five level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering and shuttering complete, for span up to 6 meters with common burnt clay F.P.S. (non modular) bricks of class designation 7.5) is derived from 10 priced inputs for 1 cum and works out to ₹19,066.10 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1:3
- Centring and shuttering (Area same as in
- item No. 6.9)
- Extra labour for lifting of material (above
- floor two level up to floor five level)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2602 | MAT | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.538 | 4,724.00 | 2,541.51 |
| SUB | Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8 | cum | 0.25 | 4,881.95 | 1,220.49 | |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
| SUB | Rate as per item no 5.9.9 of SH : Reinforced cement concrete workRate as per item 5.9.9 | sqm | 2.25 | 2,154.35 | 4,847.29 | |
| 9999 | MAT | Scaffolding | L.S. | 18.85 | 2.27 | 42.79 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 1.13 | 897.00 | 1,013.61 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.13 | 816.00 | 922.08 |
| 0115 | LAB | Coolie | day | 4.42 | 736.00 | 3,253.12 |
| 0101 | LAB | Bhisti | day | 0.2 | 816.00 | 163.20 |
| 0115 | LAB | Coolie | day | 1.13 | 736.00 | 831.68 |
- TOTAL
- 14,841.97
- Add 1 % Water charges on “W-A”
- +99.95
- TOTAL
- 14,941.92
- Add GST on “X-A” (multiplying factor 0.2127)
- +2,147.13
- TOTAL
- 17,089.05
- Add 15% CPOH on “Y-A”
- +1,836.26
- TOTAL
- 18,925.31
- Add Cess @ 1% on “Z-A”
- +140.78
- Cost for 1 cum.
- 19,066.09
- SAY
- ₹19,066.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 314
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 314. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.