CPWD Analysis of Rates · Masonry Work
Brick work 7 cm thick with common burnt clay F.P.S. (non modular) brick of class designation 7.5 in cement mortar 1:3 (1 cement : 3 coarse sand) in superstructure above plinth level and upto floor five level
- Item number
- 6.8
- Analysis basis
- Details of cost for 10sqm.
- Priced inputs
- 8
- Derived rate
- ₹865.65
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.8 — Brick work 7 cm thick with common burnt clay F.P.S. (non modular) brick of class designation 7.5 in cement mortar 1:3 (1 cement : 3 coarse sand) in superstructure above plinth level and upto floor five level — is derived from 8 priced inputs and works out to ₹865.65 after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1:3
- Extra labour for lifting of material (above
- floor two level up to floor five level)
- (10x0.07x1.13=0.79)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5Material | 1000 Nos | 0.377 | 4,724.00 | 1,780.95 |
| Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysis | cum | 0.181 | 4,881.95 | 883.63 | |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.72 | 897.00 | 645.84 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.72 | 816.00 | 587.52 |
| 0115 | CoolieLabour | day | 1.76 | 736.00 | 1,295.36 |
| 0101 | BhistiLabour | day | 0.36 | 816.00 | 293.76 |
| 9999 | Sundries and scaffoldingMaterial | L.S. | 7.15 | 2.27 | 16.23 |
| 0115 | CoolieLabour | day | 0.79 | 736.00 | 581.44 |
- TOTAL
- 6,084.73
- Add 1 % Water charges on “W”
- 60.85
- TOTAL
- 6,145.58
- Add GST on “X” (multiplying factor 0.2127)
- 1,307.16
- TOTAL
- 7,452.74
- Add 15% CPOH on “Y”
- 1,117.91
- TOTAL
- 8,570.65
- Add Cess @ 1% on “Z”
- 85.71
- Cost for 10 sqm.
- 8,656.36
- Cost for 1 sqm.
- 865.64
- Say
- 865.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 313. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.