CPWD Analysis of Rates · Masonry Work
Providing half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in cement mortar 1:3 (1 Cement : 3 coarse sand) in superstructure for closing cavity 5 to 7.5 cm wide in cavity wall complete with 10cm / 11.4 cm wide bitumen felt type 3 grade 1
- Item number
- 6.7
- Analysis basis
- Details of cost for 10m length
- Priced inputs
- 5
- Derived rate
- ₹300.75 / m length
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.7 — Providing half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in cement mortar 1:3 (1 Cement : 3 coarse sand) in superstructure for closing cavity 5 to 7.5 cm wide in cavity wall complete with 10cm / 11.4 cm wide bitumen felt type 3 grade 1 — is derived from 5 priced inputs for 10m length and works out to ₹300.75 per m length after water charges, GST, CPOH and cess. The full build-up is below.
- Half brick masonry 1:3 (Average)
- 1x10x0.27 = 2.7
- Bitumen felt type- 3 grade 1
- 1x10mx11.4m = 1.14 sqm.
- 0.06 sqm.
- Total = 1.20 sqm
- Add for wastage and overlapping @ 5% =
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item No. 6.12.1 of SH: Brick WorkRate as per item 6.12.1Sub-analysis | sqm | 2.7 | 931.75 | 2,515.73 | |
| 0322 | Bitumen felt :Type 3 grade 1Material | sqm | 1.2 | 80.00 | 96.00 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.12 | 897.00 | 107.64 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.12 | 816.00 | 97.92 |
| 0114 | BeldarLabour | day | 0.06 | 736.00 | 44.16 |
- TOTAL
- 2,861.45
- Add 1 % Water charges on “W-A”
- 3.46
- TOTAL
- 2,864.91
- Add GST on “X-A” (multiplying factor 0.2127)
- 74.27
- TOTAL
- 2,939.18
- Add 15% CPOH on “Y-A”
- 63.52
- TOTAL
- 3,002.70
- Add Cess @ 1% on “Z-A”
- 4.87
- Cost of 10 metre
- 3,007.57
- Cost for 1 metre
- 300.76
- Say
- 300.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 312. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.