Half brick masonry with non modular fly ash bricks of class designation 10, conformingio IS :12894, in super structure above plinth upto floor V level

Cement mortar 1 : 4 (1 cement : 4 coarse sand)
Item number
6.45.2
Analysis basis
10 sqm
Priced inputs
8
Derived rate
₹1,105.80/ SQM
D-01/RATE ANALYSISITEM 6.45.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.45.2 (Half brick masonry with non modular fly ash bricks of class designation 10, conformingio IS :12894, in super structure above plinth upto floor V level Cement mortar 1 : 4 (1 cement : 4 coarse sand)) is derived from 8 priced inputs for 10 sqm and works out to ₹1,105.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Extra labour for lifting of material (above
  • floor two level up to floor five level)
ANALYSIS OF RATES · ITEM 6.45.2DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7737MATFly ash bricks conforming to I.S. 128941000 Nos0.5654,500.002,542.50
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.284,211.701,179.28
9999MATSundries & ScaffoldingL.S.13.522.2730.69
0123LABMason 1st classMason 1st classday0.6897.00538.20
0124LABMason 2nd classMason 2nd classday0.6816.00489.60
0115LABCoolieday2736.001,472.00
0101LABBhistiday0.7816.00571.20
0115LABCoolieday1.29736.00949.44
BUILD-UP TO RATE
TOTAL
7,772.91
Add 1 % Water charges on “W”
+77.73
TOTAL
7,850.64
Add GST on “X” (multiplying factor 0.2127)
+1,669.83
TOTAL
9,520.47
Add 15% CPOH on “Y”
+1,428.07
TOTAL
10,948.54
Add Cess @ 1% on “Z”
+109.49
Cost for 10 sqm.
11,058.03
Cost for 1 sqm.
1,105.80
SAY
₹1,105.80
D-02/SOURCEPRINTED PAGE 340
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
340

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 340. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.