Half brick masonry with non modular fly ash bricks of class designation 10, conformingio IS :12894, in super structure above plinth upto floor V level
- Item number
- 6.45.1
- Analysis basis
- 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹1,132.50/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.45.1 (Half brick masonry with non modular fly ash bricks of class designation 10, conformingio IS :12894, in super structure above plinth upto floor V level Cement mortar 1 : 3 (1 cement : 3 coarse sand)) is derived from 8 priced inputs for 10 sqm and works out to ₹1,132.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1:3 (1 cement : 3 coarse
- sand)
- Extra labour for lifting of material (above
- floor two level up to floor five level)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7737 | MAT | Fly ash bricks conforming to I.S. 12894 | 1000 Nos | 0.565 | 4,500.00 | 2,542.50 |
| SUB | Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8 | cum | 0.28 | 4,881.95 | 1,366.95 | |
| 9999 | MAT | Sundries & Scaffolding | L.S. | 13.52 | 2.27 | 30.69 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.6 | 897.00 | 538.20 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.6 | 816.00 | 489.60 |
| 0115 | LAB | Coolie | day | 2 | 736.00 | 1,472.00 |
| 0101 | LAB | Bhisti | day | 0.7 | 816.00 | 571.20 |
| 0115 | LAB | Coolie | day | 1.29 | 736.00 | 949.44 |
- TOTAL
- 7,960.58
- Add 1 % Water charges on “W”
- +79.61
- TOTAL
- 8,040.19
- Add GST on “X” (multiplying factor 0.2127)
- +1,710.15
- TOTAL
- 9,750.34
- Add 15% CPOH on “Y”
- +1,462.55
- TOTAL
- 11,212.89
- Add Cess @ 1% on “Z”
- +112.13
- Cost for 10 sqm.
- 11,325.02
- Cost for 1 sqm.
- 1,132.50
- SAY
- ₹1,132.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 339
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 339. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.