Brick edging 7cm wide 11.4 cm deep to plinth protection with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 including grouting with cement mortar 1:4 (1 cement : 4 fine sand)

Item number
6.44
Analysis basis
100m length
Priced inputs
7
Derived rate
₹60.85/ METRE
D-01/RATE ANALYSISITEM 6.44

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.44 (Brick edging 7cm wide 11.4 cm deep to plinth protection with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 including grouting with cement mortar 1:4 (1 cement : 4 fine sand)) is derived from 7 priced inputs for 100m length and works out to ₹60.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 2nd class bricks = 42 nos. +
  • Total for 10 Nos. = 10x46.2 nos. = 462
  • Nos.
  • Add wastage @ 10% = 4.2 nos.
ANALYSIS OF RATES · ITEM 6.44DETAILS OF COST FOR 100M LENGTH
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATExcavation and disposal of surplus earthL.S.27.32.2761.97
2602MATCommon burnt clay F.P.S. (non modular) bricks class designation 7.51000 Nos0.4624,724.002,182.49
SUBRate as per Item Number 3.4 of SH: MortarsRate as per item 3.4cum0.0363,708.80133.52
0155LABMason (average)day1857.00857.00
0114LABBeldarday1736.00736.00
0101LABBhistiday0.3816.00244.80
9999MATSundriesL.S.27.32.2761.97
BUILD-UP TO RATE
TOTAL
4,277.75
Add 1 % Water charges on “W”
+42.78
TOTAL
4,320.53
Add GST on “X” (multiplying factor 0.2127)
+918.98
TOTAL
5,239.51
Add 15% CPOH on “Y”
+785.93
TOTAL
6,025.44
Add Cess @ 1% on “Z”
+60.25
Cost of 100 metre
6,085.69
Cost of 1 metre
60.86
SAY
₹60.85
D-02/SOURCEPRINTED PAGE 339
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
339

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 339. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSMASONRY WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.