Brick edging 7cm wide 11.4 cm deep to plinth protection with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 including grouting with cement mortar 1:4 (1 cement : 4 fine sand)

Item number
6.44
Analysis basis
Details of cost for 100m length
Priced inputs
7
Derived rate
60.85 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.44 Brick edging 7cm wide 11.4 cm deep to plinth protection with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 including grouting with cement mortar 1:4 (1 cement : 4 fine sand) — is derived from 7 priced inputs for 100m length and works out to ₹60.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 2nd class bricks = 42 nos. +
  • Total for 10 Nos. = 10x46.2 nos. = 462
  • Nos.
  • Add wastage @ 10% = 4.2 nos.
CodeInputUnitQuantityRate (INR)Amount (INR)
9999Excavation and disposal of surplus earthMaterialL.S.27.32.2761.97
2602Common burnt clay F.P.S. (non modular) bricks class designation 7.5Material1000 Nos0.4624,724.002,182.49
Rate as per Item Number 3.4 of SH: MortarsRate as per item 3.4Sub-analysiscum0.0363,708.80133.52
0155Mason (average)Labourday1857.00857.00
0114BeldarLabourday1736.00736.00
0101BhistiLabourday0.3816.00244.80
9999SundriesMaterialL.S.27.32.2761.97
TOTAL
4,277.75
Add 1 % Water charges on “W”
42.78
TOTAL
4,320.53
Add GST on “X” (multiplying factor 0.2127)
918.98
TOTAL
5,239.51
Add 15% CPOH on “Y”
785.93
TOTAL
6,025.44
Add Cess @ 1% on “Z”
60.25
Cost of 100 metre
6,085.69
Cost of 1 metre
60.86
Say
60.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 339. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.