CPWD Analysis of Rates · Masonry Work
Brick edging 7cm wide 11.4 cm deep to plinth protection with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 including grouting with cement mortar 1:4 (1 cement : 4 fine sand)
- Item number
- 6.44
- Analysis basis
- Details of cost for 100m length
- Priced inputs
- 7
- Derived rate
- ₹60.85 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.44 — Brick edging 7cm wide 11.4 cm deep to plinth protection with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 including grouting with cement mortar 1:4 (1 cement : 4 fine sand) — is derived from 7 priced inputs for 100m length and works out to ₹60.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- 2nd class bricks = 42 nos. +
- Total for 10 Nos. = 10x46.2 nos. = 462
- Nos.
- Add wastage @ 10% = 4.2 nos.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 9999 | Excavation and disposal of surplus earthMaterial | L.S. | 27.3 | 2.27 | 61.97 |
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5Material | 1000 Nos | 0.462 | 4,724.00 | 2,182.49 |
| Rate as per Item Number 3.4 of SH: MortarsRate as per item 3.4Sub-analysis | cum | 0.036 | 3,708.80 | 133.52 | |
| 0155 | Mason (average)Labour | day | 1 | 857.00 | 857.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 0101 | BhistiLabour | day | 0.3 | 816.00 | 244.80 |
| 9999 | SundriesMaterial | L.S. | 27.3 | 2.27 | 61.97 |
- TOTAL
- 4,277.75
- Add 1 % Water charges on “W”
- 42.78
- TOTAL
- 4,320.53
- Add GST on “X” (multiplying factor 0.2127)
- 918.98
- TOTAL
- 5,239.51
- Add 15% CPOH on “Y”
- 785.93
- TOTAL
- 6,025.44
- Add Cess @ 1% on “Z”
- 60.25
- Cost of 100 metre
- 6,085.69
- Cost of 1 metre
- 60.86
- Say
- 60.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 339. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works