CPWD Analysis of Rates · Masonry Work
Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part thereof
- Item number
- 6.41
- Analysis basis
- Details of cost for 10 sqm. per four floor
- Priced inputs
- 1
- Derived rate
- ₹181.15 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.41 — Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part thereof — is derived from 1 priced inputs for 10 sqm and works out to ₹181.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Extra labour element for lifting of materials
- above floor V level.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0115 | CoolieLabour | day | 1.73 | 736.00 | 1,273.28 |
- TOTAL
- 1,273.28
- Add 1 % Water charges on “W”
- 12.73
- TOTAL
- 1,286.01
- Add GST on “X” (multiplying factor 0.2127)
- 273.53
- TOTAL
- 1,559.54
- Add 15% CPOH on “Y”
- 233.93
- TOTAL
- 1,793.47
- Add Cess @ 1% on “Z”
- 17.93
- Cost for 10 sqm.
- 1,811.40
- Cost for 1 sqm
- 181.14
- Say
- 181.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 338. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.