Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part thereof
- Item number
- 6.41
- Analysis basis
- 10 sqm
- Priced inputs
- 1
- Derived rate
- ₹181.15/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.41 (Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part thereof) is derived from 1 priced inputs for 10 sqm and works out to ₹181.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Extra labour element for lifting of materials
- above floor V level.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0115 | LAB | Coolie | day | 1.73 | 736.00 | 1,273.28 |
- TOTAL
- 1,273.28
- Add 1 % Water charges on “W”
- +12.73
- TOTAL
- 1,286.01
- Add GST on “X” (multiplying factor 0.2127)
- +273.53
- TOTAL
- 1,559.54
- Add 15% CPOH on “Y”
- +233.93
- TOTAL
- 1,793.47
- Add Cess @ 1% on “Z”
- +17.93
- Cost for 10 sqm.
- 1,811.40
- Cost for 1 sqm
- 181.14
- SAY
- ₹181.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 338
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 338. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.