Skip to main content
R/DAR 2023

Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part thereof

Item number
6.41
Analysis basis
10 sqm
Priced inputs
1
Derived rate
₹181.15/ SQM
D-01/RATE ANALYSISITEM 6.41

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.41 (Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part thereof) is derived from 1 priced inputs for 10 sqm and works out to ₹181.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Extra labour element for lifting of materials
  • above floor V level.
ANALYSIS OF RATES · ITEM 6.41DETAILS OF COST FOR 10 SQM. PER FOUR FLOOR
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0115LABCoolieday1.73736.001,273.28
BUILD-UP TO RATE
TOTAL
1,273.28
Add 1 % Water charges on “W”
+12.73
TOTAL
1,286.01
Add GST on “X” (multiplying factor 0.2127)
+273.53
TOTAL
1,559.54
Add 15% CPOH on “Y”
+233.93
TOTAL
1,793.47
Add Cess @ 1% on “Z”
+17.93
Cost for 10 sqm.
1,811.40
Cost for 1 sqm
181.14
SAY
₹181.15
D-02/SOURCEPRINTED PAGE 338
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
338

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 338. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSMASONRY WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.