Providing and laying Gypsum panel partitions 100 mm thick with water proof Gypsum panels of size 666x500x100 mm, made of calcite phosphor Gypsum fixed with tongue and groove edges and jointed with bonding plaster as per manufacturer’s specifications in superstructure above plinth level up to floor V level. Gypsum blocks will have a minimum compressive strength of 9.3 kg/cm2
- Item number
- 6.40
- Analysis basis
- 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹1,023.60/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.40 (Providing and laying Gypsum panel partitions 100 mm thick with water proof Gypsum panels of size 666x500x100 mm, made of calcite phosphor Gypsum fixed with tongue and groove edges and jointed with bonding plaster as per manufacturer’s specifications in superstructure above plinth level up to floor V level. Gypsum blocks will have a minimum compressive strength of 9.3 kg/cm2) is derived from 5 priced inputs for 10 sqm and works out to ₹1,023.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8656 | MAT | Gypsum panel 666 X 500 X 100 mm size.Gypsum panel 666 X 500 X 100 mm size | sqm | 10 | 528.00 | 5,280.00 |
| 8657 | MAT | Bonding plaster for Gypsum panel.Bonding plaster for Gypsum panel | kg | 25 | 28.00 | 700.00 |
| 9999 | MAT | Sundries & scaffolding | L.S. | 13.52 | 2.27 | 30.69 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.5 | 897.00 | 448.50 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
- TOTAL
- 7,195.19
- Add 1 % Water charges on “W”
- +71.95
- TOTAL
- 7,267.14
- Add GST on “X” (multiplying factor 0.2127)
- +1,545.72
- TOTAL
- 8,812.86
- Add 15% CPOH on “Y”
- +1,321.93
- TOTAL
- 10,134.79
- Add Cess @ 1% on “Z”
- +101.35
- Cost for 10 sqm
- 10,236.14
- Cost for 1 sqm
- 1,023.61
- SAY
- ₹1,023.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 338
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 338. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.