CPWD Analysis of Rates · Masonry Work
Providing and laying Gypsum panel partitions 100 mm thick with water proof Gypsum panels of size 666x500x100 mm, made of calcite phosphor Gypsum fixed with tongue and groove edges and jointed with bonding plaster as per manufacturer’s specifications in superstructure above plinth level up to floor V level. Gypsum blocks will have a minimum compressive strength of 9.3 kg/cm2
- Item number
- 6.40
- Analysis basis
- Details of cost for 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹1,023.60 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.40 — Providing and laying Gypsum panel partitions 100 mm thick with water proof Gypsum panels of size 666x500x100 mm, made of calcite phosphor Gypsum fixed with tongue and groove edges and jointed with bonding plaster as per manufacturer’s specifications in superstructure above plinth level up to floor V level. Gypsum blocks will have a minimum compressive strength of 9.3 kg/cm2 — is derived from 5 priced inputs for 10 sqm and works out to ₹1,023.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8656 | Gypsum panel 666 X 500 X 100 mm size.Gypsum panel 666 X 500 X 100 mm sizeMaterial | sqm | 10 | 528.00 | 5,280.00 |
| 8657 | Bonding plaster for Gypsum panel.Bonding plaster for Gypsum panelMaterial | kg | 25 | 28.00 | 700.00 |
| 9999 | Sundries & scaffoldingMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
- TOTAL
- 7,195.19
- Add 1 % Water charges on “W”
- 71.95
- TOTAL
- 7,267.14
- Add GST on “X” (multiplying factor 0.2127)
- 1,545.72
- TOTAL
- 8,812.86
- Add 15% CPOH on “Y”
- 1,321.93
- TOTAL
- 10,134.79
- Add Cess @ 1% on “Z”
- 101.35
- Cost for 10 sqm
- 10,236.14
- Cost for 1 sqm
- 1,023.61
- Say
- 1,023.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 338. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works