Skip to main content

CPWD Analysis of Rates · Masonry Work

Providing and laying Autoclaved Aerated concrete(AAC) blocks masonry 100 mm/ 125 mm thick with Grade-1 AAC blocks of density 551 to 650 kg/cum conforming to IS:2185 (Part 3) in super structure above plinth level up to floor V level in cement mortar 1:4 (1 cement : 4 coarse sand). The rate includes providing and placing in position 2 Nos 6 mm dia M.S. bars at every third course of masonry work

Item number
6.38
Analysis basis
Details of cost for 1 cum.
Priced inputs
9
Derived rate
10,195.45 / Cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.38 Providing and laying Autoclaved Aerated concrete(AAC) blocks masonry 100 mm/ 125 mm thick with Grade-1 AAC blocks of density 551 to 650 kg/cum conforming to IS:2185 (Part 3) in super structure above plinth level up to floor V level in cement mortar 1:4 (1 cement : 4 coarse sand). The rate includes providing and placing in position 2 Nos 6 mm dia M.S. bars at every third course of masonry work — is derived from 9 priced inputs for 1 cum and works out to ₹10,195.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Reinforcement bars
  • Extra labour element required for lifting of
  • materials (above floor two level upto floor
  • five level)(0.75 x1.5 =1.13).
CodeInputUnitQuantityRate (INR)Amount (INR)
8655Autoclaved aerated concrete (AAC) blocks (grade 1 of density 551 to 650 kg/cum)Autoclaved aerated cement (AAC) blocksMaterialcum12,915.002,915.00
Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysiscum0.154,211.70631.76
9999SundriesMaterialL.S.2.732.276.20
0123Mason 1st classMason 1st classLabourday0.36897.00322.92
0124Mason 2nd classMason 2nd classLabourday0.36816.00293.76
0115CoolieLabourday1.37736.001,008.32
0101BhistiLabourday0.2816.00163.20
Rate as per item no. 5.22.1 of SH : Reinforced cement concrete workRate as per item 5.22.1Sub-analysiskg13.2107.101,413.72
0115CoolieLabourday1.13736.00831.68
TOTAL
7,586.56
Add 1 % Water charges on “W-A”
61.73
TOTAL
7,648.29
Add GST on “X-A” (multiplying factor 0.2127)
1,326.09
TOTAL
8,974.38
Add 15% CPOH on “Y-A”
1,134.10
TOTAL
10,108.48
Add Cess @ 1% on “Z-A”
86.95
Cost of 1 Cum.
10,195.43
Say
10,195.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 337. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works