Brick work with modular extruded brunt fly ash clay sewer bricks (conforming to IS : 4885) in arches in foundation and plinth in cement mortar 1:3 ( 1 cement : 3 fine sand)
- Item number
- 6.37
- Analysis basis
- Details of cost for 1 cum.
- Priced inputs
- 8
- Derived rate
- ₹13,427.30 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.37 — Brick work with modular extruded brunt fly ash clay sewer bricks (conforming to IS : 4885) in arches in foundation and plinth in cement mortar 1:3 ( 1 cement : 3 fine sand) — is derived from 8 priced inputs for 1 cum and works out to ₹13,427.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Cement Mortar 1:3 (1 cement : 3 fine
- sand).
- Centering and shuttering
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7736 | Extruded burnt flyash clay sewer bricks conforming to I.S 4885 - 1988Extruded burnt flyash clay sewer bricks conforming to I.S 4885Material | 1000 Nos | 0.487 | 5,500.00 | 2,678.50 |
| Rate as per item no 3.3 SH MortarRate as per item 3.3Sub-analysis | cum | 0.25 | 4,379.05 | 1,094.76 | |
| 9999 | SundriesMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| Rate as per item no 5.9.9 of SH : Reinforced cement concrete workRate as per item 5.9.9Sub-analysis | sqm | 2.25 | 2,154.35 | 4,847.29 | |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.42 | 897.00 | 376.74 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.42 | 816.00 | 342.72 |
| 0115 | CoolieLabour | day | 1.86 | 736.00 | 1,368.96 |
| 0101 | BhistiLabour | day | 0.2 | 816.00 | 163.20 |
- TOTAL
- 10,878.37
- Add 1 % Water charges on “W-A”
- 60.31
- TOTAL
- 10,938.68
- Add GST on “X-A” (multiplying factor 0.2127)
- 1,295.64
- TOTAL
- 12,234.32
- Add 15% CPOH on “Y-A”
- 1,108.05
- TOTAL
- 13,342.37
- Add Cess @ 1% on “Z-A”
- 84.95
- Cost per cum.
- 13,427.32
- Say
- 13,427.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 336. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works