Brick work with modular extruded brunt fly ash clay sewer bricks (conforming to IS : 4885) in arches in foundation and plinth in cement mortar 1:3 ( 1 cement : 3 fine sand)
- Item number
- 6.37
- Analysis basis
- 1 cum
- Priced inputs
- 8
- Derived rate
- ₹13,427.30/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.37 (Brick work with modular extruded brunt fly ash clay sewer bricks (conforming to IS : 4885) in arches in foundation and plinth in cement mortar 1:3 ( 1 cement : 3 fine sand)) is derived from 8 priced inputs for 1 cum and works out to ₹13,427.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Cement Mortar 1:3 (1 cement : 3 fine
- sand).
- Centering and shuttering
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7736 | MAT | Extruded burnt flyash clay sewer bricks conforming to I.S 4885 - 1988Extruded burnt flyash clay sewer bricks conforming to I.S 4885 | 1000 Nos | 0.487 | 5,500.00 | 2,678.50 |
| SUB | Rate as per item no 3.3 SH MortarRate as per item 3.3 | cum | 0.25 | 4,379.05 | 1,094.76 | |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
| SUB | Rate as per item no 5.9.9 of SH : Reinforced cement concrete workRate as per item 5.9.9 | sqm | 2.25 | 2,154.35 | 4,847.29 | |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.42 | 897.00 | 376.74 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.42 | 816.00 | 342.72 |
| 0115 | LAB | Coolie | day | 1.86 | 736.00 | 1,368.96 |
| 0101 | LAB | Bhisti | day | 0.2 | 816.00 | 163.20 |
- TOTAL
- 10,878.37
- Add 1 % Water charges on “W-A”
- +60.31
- TOTAL
- 10,938.68
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,295.64
- TOTAL
- 12,234.32
- Add 15% CPOH on “Y-A”
- +1,108.05
- TOTAL
- 13,342.37
- Add Cess @ 1% on “Z-A”
- +84.95
- Cost per cum.
- 13,427.32
- SAY
- ₹13,427.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 336
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 336. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.