Brick work with modular extruded brunt fly ash clay sewer bricks (conforming to IS : 4885) in arches in foundation and plinth in cement mortar 1:3 ( 1 cement : 3 fine sand)

Item number
6.37
Analysis basis
1 cum
Priced inputs
8
Derived rate
₹13,427.30/ CUM
D-01/RATE ANALYSISITEM 6.37

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.37 (Brick work with modular extruded brunt fly ash clay sewer bricks (conforming to IS : 4885) in arches in foundation and plinth in cement mortar 1:3 ( 1 cement : 3 fine sand)) is derived from 8 priced inputs for 1 cum and works out to ₹13,427.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement Mortar 1:3 (1 cement : 3 fine
  • sand).
  • Centering and shuttering
ANALYSIS OF RATES · ITEM 6.37DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7736MATExtruded burnt flyash clay sewer bricks conforming to I.S 4885 - 1988Extruded burnt flyash clay sewer bricks conforming to I.S 48851000 Nos0.4875,500.002,678.50
SUBRate as per item no 3.3 SH MortarRate as per item 3.3cum0.254,379.051,094.76
9999MATSundriesL.S.2.732.276.20
SUBRate as per item no 5.9.9 of SH : Reinforced cement concrete workRate as per item 5.9.9sqm2.252,154.354,847.29
0123LABMason 1st classMason 1st classday0.42897.00376.74
0124LABMason 2nd classMason 2nd classday0.42816.00342.72
0115LABCoolieday1.86736.001,368.96
0101LABBhistiday0.2816.00163.20
BUILD-UP TO RATE
TOTAL
10,878.37
Add 1 % Water charges on “W-A”
+60.31
TOTAL
10,938.68
Add GST on “X-A” (multiplying factor 0.2127)
+1,295.64
TOTAL
12,234.32
Add 15% CPOH on “Y-A”
+1,108.05
TOTAL
13,342.37
Add Cess @ 1% on “Z-A”
+84.95
Cost per cum.
13,427.32
SAY
₹13,427.30
D-02/SOURCEPRINTED PAGE 336
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
336

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 336. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSMASONRY WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.