CPWD Analysis of Rates · Masonry Work

Brick work with modular extruded brunt fly ash clay sewer bricks (conforming to IS : 4885) in arches in foundation and plinth in cement mortar 1:3 ( 1 cement : 3 fine sand)

Item number
6.37
Analysis basis
Details of cost for 1 cum.
Priced inputs
8
Derived rate
13,427.30 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.37 Brick work with modular extruded brunt fly ash clay sewer bricks (conforming to IS : 4885) in arches in foundation and plinth in cement mortar 1:3 ( 1 cement : 3 fine sand) — is derived from 8 priced inputs for 1 cum and works out to ₹13,427.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement Mortar 1:3 (1 cement : 3 fine
  • sand).
  • Centering and shuttering
CodeInputUnitQuantityRate (INR)Amount (INR)
7736Extruded burnt flyash clay sewer bricks conforming to I.S 4885 - 1988Extruded burnt flyash clay sewer bricks conforming to I.S 4885Material1000 Nos0.4875,500.002,678.50
Rate as per item no 3.3 SH MortarRate as per item 3.3Sub-analysiscum0.254,379.051,094.76
9999SundriesMaterialL.S.2.732.276.20
Rate as per item no 5.9.9 of SH : Reinforced cement concrete workRate as per item 5.9.9Sub-analysissqm2.252,154.354,847.29
0123Mason 1st classMason 1st classLabourday0.42897.00376.74
0124Mason 2nd classMason 2nd classLabourday0.42816.00342.72
0115CoolieLabourday1.86736.001,368.96
0101BhistiLabourday0.2816.00163.20
TOTAL
10,878.37
Add 1 % Water charges on “W-A”
60.31
TOTAL
10,938.68
Add GST on “X-A” (multiplying factor 0.2127)
1,295.64
TOTAL
12,234.32
Add 15% CPOH on “Y-A”
1,108.05
TOTAL
13,342.37
Add Cess @ 1% on “Z-A”
84.95
Cost per cum.
13,427.32
Say
13,427.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 336. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.