Brick work with modular extruded brunt fly ash clay sewer bricks (Conforming to IS: 4885) in cement mortar 1:4 (1 cement : 4 coarse sand) in foundation and plinth

Cement Mortar 1:4 ( 1 cement : 4 coarse sand)

Item number
6.36.1
Analysis basis
Details of cost for 1 cum.
Priced inputs
7
Derived rate
7,197.75 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.36.1 Brick work with modular extruded brunt fly ash clay sewer bricks (Conforming to IS: 4885) in cement mortar 1:4 (1 cement : 4 coarse sand) in foundation and plinth : Cement Mortar 1:4 ( 1 cement : 4 coarse sand) — is derived from 7 priced inputs for 1 cum and works out to ₹7,197.75 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
7736Extruded burnt flyash clay sewer bricks conforming to I.S 4885 - 1988Extruded burnt flyash clay sewer bricks conforming to I.S 4885Material1000 Nos0.4875,500.002,678.50
Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysiscum0.224,211.70926.57
9999SundriesMaterialL.S.2.732.276.20
0123Mason 1st classMason 1st classLabourday0.33897.00296.01
0124Mason 2nd classMason 2nd classLabourday0.33816.00269.28
0115CoolieLabourday1736.00736.00
0101BhistiLabourday0.18816.00146.88
TOTAL
5,059.44
Add 1 % Water charges on “W”
50.59
TOTAL
5,110.03
Add GST on “X” (multiplying factor 0.2127)
1,086.90
TOTAL
6,196.93
Add 15% CPOH on “Y”
929.54
TOTAL
7,126.47
Add Cess @ 1% on “Z”
71.26
Cost per cum.
7,197.73
Say
7,197.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 336. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.