Brick work with modular extruded brunt fly ash clay sewer bricks (Conforming to IS: 4885) in cement mortar 1:4 (1 cement : 4 coarse sand) in foundation and plinth

Cement Mortar 1:4 ( 1 cement : 4 coarse sand)
Item number
6.36.1
Analysis basis
1 cum
Priced inputs
7
Derived rate
₹7,197.75/ CUM
D-01/RATE ANALYSISITEM 6.36.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.36.1 (Brick work with modular extruded brunt fly ash clay sewer bricks (Conforming to IS: 4885) in cement mortar 1:4 (1 cement : 4 coarse sand) in foundation and plinth : Cement Mortar 1:4 ( 1 cement : 4 coarse sand)) is derived from 7 priced inputs for 1 cum and works out to ₹7,197.75 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
ANALYSIS OF RATES · ITEM 6.36.1DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7736MATExtruded burnt flyash clay sewer bricks conforming to I.S 4885 - 1988Extruded burnt flyash clay sewer bricks conforming to I.S 48851000 Nos0.4875,500.002,678.50
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.224,211.70926.57
9999MATSundriesL.S.2.732.276.20
0123LABMason 1st classMason 1st classday0.33897.00296.01
0124LABMason 2nd classMason 2nd classday0.33816.00269.28
0115LABCoolieday1736.00736.00
0101LABBhistiday0.18816.00146.88
BUILD-UP TO RATE
TOTAL
5,059.44
Add 1 % Water charges on “W”
+50.59
TOTAL
5,110.03
Add GST on “X” (multiplying factor 0.2127)
+1,086.90
TOTAL
6,196.93
Add 15% CPOH on “Y”
+929.54
TOTAL
7,126.47
Add Cess @ 1% on “Z”
+71.26
Cost per cum.
7,197.73
SAY
₹7,197.75
D-02/SOURCEPRINTED PAGE 336
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
336

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 336. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.