CPWD Analysis of Rates · Masonry Work

Brick work with modular calcium silicate bricks machine moulded conforming to IS:4139, class designation 10 average compressive strength in super structure above plinth level up to floor V level in

Cement mortar 1:6 (1 cement : 6 Coarse sand)

Item number
6.35.2
Analysis basis
Details of cost for 1 cum.
Priced inputs
9
Derived rate
9,583.95 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.35.2 Brick work with modular calcium silicate bricks machine moulded conforming to IS:4139, class designation 10 average compressive strength in super structure above plinth level up to floor V level in : Cement mortar 1:6 (1 cement : 6 Coarse sand) — is derived from 9 priced inputs for 1 cum and works out to ₹9,583.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1 : 6 (1 cement : 6 coarse
  • sand)
  • Extra labour element required for lifting of
  • materials above floor two level upto floor
  • V level (0.75 x 1.5 = 1.13)
CodeInputUnitQuantityRate (INR)Amount (INR)
7738Calcium Silicate Bricks machine moulded conforming to I.S. 4139 - 1989Calcium Silicate Bricks machine moulded conforming to I.S. 4139Material1000 Nos0.4875,700.002,775.90
Rate as per Item Number 3.11 of SH: MortarsRate as per item 3.11Sub-analysiscum0.223,541.40779.11
9999SundriesMaterialL.S.2.732.276.20
0123Mason 1st classMason 1st classLabourday0.47897.00421.59
0124Mason 2nd classMason 2nd classLabourday0.47816.00383.52
0115CoolieLabourday1.8736.001,324.80
0101BhistiLabourday0.2816.00163.20
9999ScaffoldingMaterialL.S.22.362.2750.76
0115CoolieLabourday1.13736.00831.68
TOTAL
6,736.76
Add 1 % Water charges on “W”
67.37
TOTAL
6,804.13
Add GST on “X” (multiplying factor 0.2127)
1,447.24
TOTAL
8,251.37
Add 15% CPOH on “Y”
1,237.71
TOTAL
9,489.08
Add Cess @ 1% on “Z”
94.89
Cost per cum.
9,583.97
Say
9,583.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 335. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.