Skip to main content
R/DAR 2023

Providing and laying Autoclaved Aerated concrete(AAC) blocks masonry with 150mm to 300 mm thick with Grade-1 AAC blocks of density 551 to 650 kg/cum conforming to IS:2185 (Part 3) in super structure above plinth level up to floor V level with RCC band at sill level and lintel level with approved block laying polymer modified adhesive mortar all complete as per direction of Engineer-in-Charge. (The payment of RCC band and reinforcement shall be made for seperately)

Item number
6.47
Analysis basis
1 cum
Priced inputs
7
Derived rate
₹8,333.65/ CUM
D-01/RATE ANALYSISITEM 6.47

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.47 (Providing and laying Autoclaved Aerated concrete(AAC) blocks masonry with 150mm to 300 mm thick with Grade-1 AAC blocks of density 551 to 650 kg/cum conforming to IS:2185 (Part 3) in super structure above plinth level up to floor V level with RCC band at sill level and lintel level with approved block laying polymer modified adhesive mortar all complete as per direction of Engineer-in-Charge. (The payment of RCC band and reinforcement shall be made for seperately)) is derived from 7 priced inputs for 1 cum and works out to ₹8,333.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Extra labour element required for lifting of
  • materials (above floor two level upto floor
  • five level) (0.75x1.50 = 1.13)
ANALYSIS OF RATES · ITEM 6.47DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8655MATAutoclaved aerated concrete (AAC) blocks (grade 1 of density 551 to 650 kg/ cum)Autoclaved aerated cement (AAC) blockscum12,915.002,915.00
0357MATPolymer modified adhesive mortarKg3016.00480.00
9999MATSundriesL.S.2.732.276.20
0123LABMason (brick layer) 1 st classMason 1st classday0.36897.00322.92
0124LABMason 2nd classMason 2nd classday0.36816.00293.76
0115LABCoolieday1.37736.001,008.32
0115LABCoolieday1.13736.00831.68
BUILD-UP TO RATE
TOTAL
5,857.88
Add 1 % Water charges on “W”
+58.58
TOTAL
5,916.46
Add GST on “X” (multiplying factor 0.2127)
+1,258.43
TOTAL
7,174.89
Add 15% CPOH on “Y”
+1,076.23
TOTAL
8,251.12
Add Cess @ 1% on “Z”
+82.51
Cost of 1 cum
8,333.63
SAY
₹8,333.65
D-02/SOURCEPRINTED PAGE 341
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
341

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 341. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSMASONRY WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.