Providing and laying Autoclaved Aerated concrete(AAC) blocks masonry with 150mm to 300 mm thick with Grade-1 AAC blocks of density 551 to 650 kg/cum conforming to IS:2185 (Part 3) in super structure above plinth level up to floor V level with RCC band at sill level and lintel level with approved block laying polymer modified adhesive mortar all complete as per direction of Engineer-in-Charge. (The payment of RCC band and reinforcement shall be made for seperately)
- Item number
- 6.47
- Analysis basis
- 1 cum
- Priced inputs
- 7
- Derived rate
- ₹8,333.65/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.47 (Providing and laying Autoclaved Aerated concrete(AAC) blocks masonry with 150mm to 300 mm thick with Grade-1 AAC blocks of density 551 to 650 kg/cum conforming to IS:2185 (Part 3) in super structure above plinth level up to floor V level with RCC band at sill level and lintel level with approved block laying polymer modified adhesive mortar all complete as per direction of Engineer-in-Charge. (The payment of RCC band and reinforcement shall be made for seperately)) is derived from 7 priced inputs for 1 cum and works out to ₹8,333.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Extra labour element required for lifting of
- materials (above floor two level upto floor
- five level) (0.75x1.50 = 1.13)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8655 | MAT | Autoclaved aerated concrete (AAC) blocks (grade 1 of density 551 to 650 kg/ cum)Autoclaved aerated cement (AAC) blocks | cum | 1 | 2,915.00 | 2,915.00 |
| 0357 | MAT | Polymer modified adhesive mortar | Kg | 30 | 16.00 | 480.00 |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
| 0123 | LAB | Mason (brick layer) 1 st classMason 1st class | day | 0.36 | 897.00 | 322.92 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.36 | 816.00 | 293.76 |
| 0115 | LAB | Coolie | day | 1.37 | 736.00 | 1,008.32 |
| 0115 | LAB | Coolie | day | 1.13 | 736.00 | 831.68 |
- TOTAL
- 5,857.88
- Add 1 % Water charges on “W”
- +58.58
- TOTAL
- 5,916.46
- Add GST on “X” (multiplying factor 0.2127)
- +1,258.43
- TOTAL
- 7,174.89
- Add 15% CPOH on “Y”
- +1,076.23
- TOTAL
- 8,251.12
- Add Cess @ 1% on “Z”
- +82.51
- Cost of 1 cum
- 8,333.63
- SAY
- ₹8,333.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 341
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 341. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.