CPWD Analysis of Rates · Masonry Work

Honey-comb brick work 10 / 11.4 cm thick with common burnt clay bricks of class designation 7.5 in super structure above plinth level upto floor V level with cement mortar 1:4 (1 cement : 4 coarse sand)

Item number
6.23
Analysis basis
Details of cost for 1sqm. of Honey comb
Priced inputs
2
Derived rate
711.50 / sqm. of

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.23 Honey-comb brick work 10 / 11.4 cm thick with common burnt clay bricks of class designation 7.5 in super structure above plinth level upto floor V level with cement mortar 1:4 (1 cement : 4 coarse sand) — is derived from 2 priced inputs for 1sqm. of and works out to ₹711.50 per sqm. of after water charges, GST, CPOH and cess. The full build-up is below.

  • brick worksBrick work, with bricks of class designation 75, in cement mortar 1:4 (1 Cement :
  • 4 Coarse sand) in superstructure
  • 1 m x 1 x 0.143 m x 4.5/7.5 = 0.069 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item No 6.4.1 of SH :- Brick workRate as per item 6.4.1Sub-analysiscum0.0699,344.35644.76
9999Extra for delay due to fine workMaterialL.S.20.672.2746.92
TOTAL
691.68
Add 1 % Water charges on “W-A”
0.47
TOTAL
692.15
Add GST on “X-A” (multiplying factor 0.2127)
10.08
TOTAL
702.23
Add 15% CPOH on “Y-A”
8.62
TOTAL
710.85
Add Cess @ 1% on “Z-A”
0.66
Cost for 1 sqm.
711.51
Say
711.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 323. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.