CPWD Analysis of Rates · Masonry Work
Extra for laying brick work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE :- The quantity will be calculated by multiplying the depth measured from sub - soil water level up to the centre of gravity of brick work under sub - soil water with the quantity of brick work in cum. executed under the sub - soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, (0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored)
- Item number
- 6.24
- Analysis basis
- Details of cost for 4.2 cum per 1 m depth
- Priced inputs
- 2
- Derived rate
- ₹1,098.80 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.24 — Extra for laying brick work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE :- The quantity will be calculated by multiplying the depth measured from sub - soil water level up to the centre of gravity of brick work under sub - soil water with the quantity of brick work in cum. executed under the sub - soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, (0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored) — is derived from 2 priced inputs for 4.2 cum and works out to ₹1,098.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- (14 cum per 0.3m depth)
- Quantity of concrete = 14 cum.
- pumping hours = 3 hrs. on 0.375 day.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0011 | Hire charges of Pumpset of capacity 4000 litres/hourHire charges of Pump set of capacity 4000 litres/hourMachinery | day | 0.375 | 800.00 | 300.00 |
| 0114 | BeldarLabour | day | 4 | 736.00 | 2,944.00 |
- TOTAL
- 3,244.00
- Add 1 % Water charges on “W”
- 32.44
- TOTAL
- 3,276.44
- Add GST on “X” (multiplying factor 0.2127)
- 696.90
- TOTAL
- 3,973.34
- Add 15% CPOH on “Y”
- 596.00
- TOTAL
- 4,569.34
- Add Cess @ 1% on “Z”
- 45.69
- Cost of 4.2cum per 1 metre depth
- 4,615.03
- Cost of cum per metre depth
- 1,098.82
- Say
- 1,098.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 324. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works