CPWD Analysis of Rates · Masonry Work

Tile brick masonry with common burnt clay F.P.S. (non modular) tile bricks of class designation 10 in gauged arch work in superstructure above plinth and upto floor five level in cement mortar 1:4 (1 cement : 4 coarse sand) including centering and shuttering complete

Item number
6.21
Analysis basis
Details of cost for 1 cum.
Priced inputs
10
Derived rate
23,019.75 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.21 Tile brick masonry with common burnt clay F.P.S. (non modular) tile bricks of class designation 10 in gauged arch work in superstructure above plinth and upto floor five level in cement mortar 1:4 (1 cement : 4 coarse sand) including centering and shuttering complete — is derived from 10 priced inputs for 1 cum and works out to ₹23,019.75 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Centering and shuttering, area same as in
  • item no. 6.9
  • Extra labour for lifting of material (above
  • floor two level up to floor five level)
CodeInputUnitQuantityRate (INR)Amount (INR)
1984Common burnt clay F.P.S. (non modular) bricks tile class designation 10Common burnt clay F.P.S. bricks tile class designation 10Material1000 Nos0.7914,750.003,757.25
Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysiscum0.354,211.701,474.10
9999Sundries and shutteringMaterialL.S.5.462.2712.39
Rate as per item no 5.9.9 of SH : Reinforced cement concrete workRate as per item 5.9.9Sub-analysissqm2.252,154.354,847.29
9999ScaffoldingMaterialL.S.18.852.2742.79
0123Mason 1st classMason 1st classLabourday1.5897.001,345.50
0124Mason 2nd classMason 2nd classLabourday1.5816.001,224.00
0115CoolieLabourday5.33736.003,922.88
0101BhistiLabourday0.2816.00163.20
0115CoolieLabourday1.13736.00831.68
TOTAL
17,621.08
Add 1 % Water charges on “W-A”
127.74
TOTAL
17,748.82
Add GST on “X-A” (multiplying factor 0.2127)
2,744.16
TOTAL
20,492.98
Add 15% CPOH on “Y-A”
2,346.85
TOTAL
22,839.83
Add Cess @ 1% on “Z-A”
179.93
Cost for 1 cum.
23,019.76
Say
23,019.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 322. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.