Tile brick masonry with common burnt clay F.P.S. (non modular) tile bricks of class designation 10 in plain arch work in superstructure above plinth and upto floor five level in cement mortar 1:4 (1 cement : 4 coarse sand) including centering and shuttering complete
- Item number
- 6.20
- Analysis basis
- 1 cum
- Priced inputs
- 10
- Derived rate
- ₹18,975.15/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.20 (Tile brick masonry with common burnt clay F.P.S. (non modular) tile bricks of class designation 10 in plain arch work in superstructure above plinth and upto floor five level in cement mortar 1:4 (1 cement : 4 coarse sand) including centering and shuttering complete) is derived from 10 priced inputs for 1 cum and works out to ₹18,975.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Centering and shuttering, area same as in
- item no. 6.9
- Extra labour for lifting of material (above
- floor two level up to floor five level)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1984 | MAT | Common burnt clay F.P.S. (non modular) bricks tile class designation 10Common burnt clay F.P.S. bricks tile class designation 10 | 1000 Nos | 0.777 | 4,750.00 | 3,690.75 |
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.35 | 4,211.70 | 1,474.10 | |
| 9999 | MAT | Sundries | L.S. | 5.46 | 2.27 | 12.39 |
| SUB | Rate as per item no 5.9.9 of SH : Reinforced cement concrete workRate as per item 5.9.9 | sqm | 2.25 | 2,154.35 | 4,847.29 | |
| 9999 | MAT | Scaffolding | L.S. | 18.85 | 2.27 | 42.79 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.79 | 897.00 | 708.63 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.79 | 816.00 | 644.64 |
| 0115 | LAB | Coolie | day | 3.21 | 736.00 | 2,362.56 |
| 0101 | LAB | Bhisti | day | 0.2 | 816.00 | 163.20 |
| 0115 | LAB | Coolie | day | 1.13 | 736.00 | 831.68 |
- TOTAL
- 14,778.03
- Add 1 % Water charges on “W-A”
- +99.31
- TOTAL
- 14,877.34
- Add GST on “X-A” (multiplying factor 0.2127)
- +2,133.39
- TOTAL
- 17,010.73
- Add 15% CPOH on “Y-A”
- +1,824.52
- TOTAL
- 18,835.25
- Add Cess @ 1% on “Z-A”
- +139.88
- Cost for 1 cum.
- 18,975.13
- SAY
- ₹18,975.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 321
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 321. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.