Skip to main content
R/DAR 2023

Tile brick masonry with common burnt clay F.P.S. (non modular) tile bricks of class designation 10 in plain arch work in superstructure above plinth and upto floor five level in cement mortar 1:4 (1 cement : 4 coarse sand) including centering and shuttering complete

Item number
6.20
Analysis basis
1 cum
Priced inputs
10
Derived rate
₹18,975.15/ CUM
D-01/RATE ANALYSISITEM 6.20

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 6.20 (Tile brick masonry with common burnt clay F.P.S. (non modular) tile bricks of class designation 10 in plain arch work in superstructure above plinth and upto floor five level in cement mortar 1:4 (1 cement : 4 coarse sand) including centering and shuttering complete) is derived from 10 priced inputs for 1 cum and works out to ₹18,975.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Centering and shuttering, area same as in
  • item no. 6.9
  • Extra labour for lifting of material (above
  • floor two level up to floor five level)
ANALYSIS OF RATES · ITEM 6.20DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1984MATCommon burnt clay F.P.S. (non modular) bricks tile class designation 10Common burnt clay F.P.S. bricks tile class designation 101000 Nos0.7774,750.003,690.75
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.354,211.701,474.10
9999MATSundriesL.S.5.462.2712.39
SUBRate as per item no 5.9.9 of SH : Reinforced cement concrete workRate as per item 5.9.9sqm2.252,154.354,847.29
9999MATScaffoldingL.S.18.852.2742.79
0123LABMason 1st classMason 1st classday0.79897.00708.63
0124LABMason 2nd classMason 2nd classday0.79816.00644.64
0115LABCoolieday3.21736.002,362.56
0101LABBhistiday0.2816.00163.20
0115LABCoolieday1.13736.00831.68
BUILD-UP TO RATE
TOTAL
14,778.03
Add 1 % Water charges on “W-A”
+99.31
TOTAL
14,877.34
Add GST on “X-A” (multiplying factor 0.2127)
+2,133.39
TOTAL
17,010.73
Add 15% CPOH on “Y-A”
+1,824.52
TOTAL
18,835.25
Add Cess @ 1% on “Z-A”
+139.88
Cost for 1 cum.
18,975.13
SAY
₹18,975.15
D-02/SOURCEPRINTED PAGE 321
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
321

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 321. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSMASONRY WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.