R/DAR 2023

Cement concrete pavement with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including finishing complete

Item number
11.7
Analysis basis
one cum
Priced inputs
5
Derived rate
₹8,595.15/ CUM
D-01/RATE ANALYSISITEM 11.7

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.7 (Cement concrete pavement with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including finishing complete) is derived from 5 priced inputs for one cum and works out to ₹8,595.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:2:4
  • Extra labour for laying in floors etc.
ANALYSIS OF RATES · ITEM 11.7DETAILS OF COST FOR ONE CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item No.4.1.3 of S.H.Concrete WorkRate as per item 4.1.3cum17,878.507,878.50
0124LABMason 2nd classMason 2nd classday0.35816.00285.60
0114LABBeldarday0.18736.00132.48
0101LABBhistiday0.05816.0040.80
9999MATSundriesL.S.19.762.2744.86
BUILD-UP TO RATE
TOTAL
8,382.24
Add 1 % Water charges on “W-A”
+5.04
TOTAL
8,387.28
Add GST on “X-A” (multiplying factor 0.2127)
+108.22
TOTAL
8,495.50
Add 15% CPOH on “Y-A”
+92.55
TOTAL
8,588.05
Add Cess @ 1% on “Z-A”
+7.10
Cost of 1 Cum.
8,595.15
SAY
₹8,595.15
D-02/SOURCEPRINTED PAGE 759
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
759

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 759. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.