Cement plaster skirting up to 30 cm height, with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement

18 mm thick
Item number
11.6.1
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹662.05/ SQM
D-01/RATE ANALYSISITEM 11.6.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.6.1 (Cement plaster skirting up to 30 cm height, with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement 18 mm thick) is derived from 6 priced inputs for 10 sqm and works out to ₹662.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:3 = 0.205 cum+
  • = 0.235 cum.
  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
  • Add for rounding corners = 0.030 cum
ANALYSIS OF RATES · ITEM 11.6.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum0.2354,881.951,147.26
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.025,156.00103.12
0124LABMason 2nd classMason 2nd classday1.88816.001,534.08
0115LABCoolieday1.88736.001,383.68
0101LABBhistiday0.54816.00440.64
9999MATSundriesL.S.19.762.2744.86
BUILD-UP TO RATE
TOTAL
4,653.64
Add 1 % Water charges on “W”
+46.54
TOTAL
4,700.18
Add GST on “X” (multiplying factor 0.2127)
+999.73
TOTAL
5,699.91
Add 15% CPOH on “Y”
+854.99
TOTAL
6,554.90
Add Cess @ 1% on “Z”
+65.55
Cost of 10 sqm.
6,620.45
Cost of 1 sqm.
662.05
SAY
₹662.05
D-02/SOURCEPRINTED PAGE 758
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
758

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 758. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.