Cement plaster skirting up to 30 cm height, with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement
- Item number
- 11.6.1
- Analysis basis
- 10 sqm
- Priced inputs
- 6
- Derived rate
- ₹662.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.6.1 (Cement plaster skirting up to 30 cm height, with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement 18 mm thick) is derived from 6 priced inputs for 10 sqm and works out to ₹662.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Cement mortar 1:3 = 0.205 cum+
- = 0.235 cum.
- Cement mortar 1:3 (1 cement : 3 coarse
- sand)
- Add for rounding corners = 0.030 cum
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8 | cum | 0.235 | 4,881.95 | 1,147.26 | |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.02 | 5,156.00 | 103.12 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.88 | 816.00 | 1,534.08 |
| 0115 | LAB | Coolie | day | 1.88 | 736.00 | 1,383.68 |
| 0101 | LAB | Bhisti | day | 0.54 | 816.00 | 440.64 |
| 9999 | MAT | Sundries | L.S. | 19.76 | 2.27 | 44.86 |
- TOTAL
- 4,653.64
- Add 1 % Water charges on “W”
- +46.54
- TOTAL
- 4,700.18
- Add GST on “X” (multiplying factor 0.2127)
- +999.73
- TOTAL
- 5,699.91
- Add 15% CPOH on “Y”
- +854.99
- TOTAL
- 6,554.90
- Add Cess @ 1% on “Z”
- +65.55
- Cost of 10 sqm.
- 6,620.45
- Cost of 1 sqm.
- 662.05
- SAY
- ₹662.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 758
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 758. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.