62 mm thick cement concrete flooring with concrete hardener topping, under layer 50 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size) and top layer 12mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate, 6mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacture’s specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete

Item number
11.5
Analysis basis
Details of cost for 10 sqm.
Priced inputs
13
Derived rate
1,056.15 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.5 62 mm thick cement concrete flooring with concrete hardener topping, under layer 50 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size) and top layer 12mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate, 6mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacture’s specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete — is derived from 13 priced inputs for 10 sqm and works out to ₹1,056.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.3341,425.00475.95
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.1111,400.00155.40
0982Coarse sand (zone III)Materialcum0.2221,450.00321.90
0298Stone Aggregate (Single size) : 06 mm nominal sizeMaterialcum0.1151,425.00163.88
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.2435,156.001,252.91
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.025,156.00103.12
7254Hardening compoundMateriallitre2.4439.0095.16
9977Carriage of Hardening compoundMaterialL.S.2.732.276.20
0124Mason 2nd classMason 2nd classLabourday2.15816.001,754.40
0114BeldarLabourday1.86736.001,368.96
0115CoolieLabourday1.88736.001,383.68
0101BhistiLabourday0.27816.00220.32
9999SundriesMaterialL.S.53.822.27122.17
TOTAL
7,424.05
Add 1 % Water charges on “W”
74.24
TOTAL
7,498.29
Add GST on “X” (multiplying factor 0.2127)
1,594.89
TOTAL
9,093.18
Add 15% CPOH on “Y”
1,363.98
TOTAL
10,457.16
Add Cess @ 1% on “Z”
104.57
Cost of 10 sqm.
10,561.73
Cost of 1 sqm.
1,056.17
Say
1,056.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 758. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.