CPWD Analysis of Rates · Flooring
62 mm thick cement concrete flooring with concrete hardener topping, under layer 50 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size) and top layer 12mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate, 6mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacture’s specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete
- Item number
- 11.5
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 13
- Derived rate
- ₹1,056.15 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.5 — 62 mm thick cement concrete flooring with concrete hardener topping, under layer 50 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size) and top layer 12mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate, 6mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacture’s specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete — is derived from 13 priced inputs for 10 sqm and works out to ₹1,056.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0295 | Stone Aggregate (Single size) : 20 mm nominal sizeMaterial | cum | 0.334 | 1,425.00 | 475.95 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal sizeMaterial | cum | 0.111 | 1,400.00 | 155.40 |
| 0982 | Coarse sand (zone III)Material | cum | 0.222 | 1,450.00 | 321.90 |
| 0298 | Stone Aggregate (Single size) : 06 mm nominal sizeMaterial | cum | 0.115 | 1,425.00 | 163.88 |
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 0.243 | 5,156.00 | 1,252.91 |
| 0367 | Portland CementPortland Cement (OPC-43 Grade)Material | tonne | 0.02 | 5,156.00 | 103.12 |
| 7254 | Hardening compoundMaterial | litre | 2.44 | 39.00 | 95.16 |
| 9977 | Carriage of Hardening compoundMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 2.15 | 816.00 | 1,754.40 |
| 0114 | BeldarLabour | day | 1.86 | 736.00 | 1,368.96 |
| 0115 | CoolieLabour | day | 1.88 | 736.00 | 1,383.68 |
| 0101 | BhistiLabour | day | 0.27 | 816.00 | 220.32 |
| 9999 | SundriesMaterial | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 7,424.05
- Add 1 % Water charges on “W”
- 74.24
- TOTAL
- 7,498.29
- Add GST on “X” (multiplying factor 0.2127)
- 1,594.89
- TOTAL
- 9,093.18
- Add 15% CPOH on “Y”
- 1,363.98
- TOTAL
- 10,457.16
- Add Cess @ 1% on “Z”
- 104.57
- Cost of 10 sqm.
- 10,561.73
- Cost of 1 sqm.
- 1,056.17
- Say
- 1,056.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 758. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.