Skip to main content
R/DAR 2023

52 mm thick cement concrete flooring with concrete hardener topping, under layer 40 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate 6 mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacturer’s specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete

Item number
11.4
Analysis basis
10 sqm
Priced inputs
13
Derived rate
₹978.45/ SQM
D-01/RATE ANALYSISITEM 11.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.4 (52 mm thick cement concrete flooring with concrete hardener topping, under layer 40 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate 6 mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacturer’s specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete) is derived from 13 priced inputs for 10 sqm and works out to ₹978.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 11.4DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum0.2671,425.00380.48
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.0891,400.00124.60
0982MATCoarse sand (zone III)cum0.1781,450.00258.10
0298MATStone Aggregate (Single size) : 06 mm nominal sizecum0.1151,425.00163.88
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.2115,156.001,087.92
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.025,156.00103.12
7254MATHardening compoundlitre2.4439.0095.16
9977MATCarriage of hard creteL.S.2.732.276.20
0124LABMason 2nd classMason 2nd classday2.15816.001,754.40
0114LABBeldarday1.6736.001,177.60
0115LABCoolieday1.88736.001,383.68
0101LABBhistiday0.27816.00220.32
9999MATSundriesL.S.53.822.27122.17
BUILD-UP TO RATE
TOTAL
6,877.63
Add 1 % Water charges on “W”
+68.78
TOTAL
6,946.41
Add GST on “X” (multiplying factor 0.2127)
+1,477.50
TOTAL
8,423.91
Add 15% CPOH on “Y”
+1,263.59
TOTAL
9,687.50
Add Cess @ 1% on “Z”
+96.88
Cost of 10 sqm.
9,784.38
Cost of 1 sqm.
978.44
SAY
₹978.45
D-02/SOURCEPRINTED PAGE 757
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
757

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 757. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.