CPWD Analysis of Rates · Flooring

52 mm thick cement concrete flooring with concrete hardener topping, under layer 40 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate 6 mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacturer’s specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete

Item number
11.4
Analysis basis
Details of cost for 10 sqm.
Priced inputs
13
Derived rate
978.45 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.4 52 mm thick cement concrete flooring with concrete hardener topping, under layer 40 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate 6 mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacturer’s specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete — is derived from 13 priced inputs for 10 sqm and works out to ₹978.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.2671,425.00380.48
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.0891,400.00124.60
0982Coarse sand (zone III)Materialcum0.1781,450.00258.10
0298Stone Aggregate (Single size) : 06 mm nominal sizeMaterialcum0.1151,425.00163.88
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.2115,156.001,087.92
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.025,156.00103.12
7254Hardening compoundMateriallitre2.4439.0095.16
9977Carriage of hard creteMaterialL.S.2.732.276.20
0124Mason 2nd classMason 2nd classLabourday2.15816.001,754.40
0114BeldarLabourday1.6736.001,177.60
0115CoolieLabourday1.88736.001,383.68
0101BhistiLabourday0.27816.00220.32
9999SundriesMaterialL.S.53.822.27122.17
TOTAL
6,877.63
Add 1 % Water charges on “W”
68.78
TOTAL
6,946.41
Add GST on “X” (multiplying factor 0.2127)
1,477.50
TOTAL
8,423.91
Add 15% CPOH on “Y”
1,263.59
TOTAL
9,687.50
Add Cess @ 1% on “Z”
96.88
Cost of 10 sqm.
9,784.38
Cost of 1 sqm.
978.44
Say
978.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 757. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.