CPWD Analysis of Rates · Flooring

Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete

40 mm thick with 20 mm nominal size stone aggregate

Item number
11.3.1
Analysis basis
Details of cost for 10 sqm.
Priced inputs
10
Derived rate
614.20 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.3.1 Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete 40 mm thick with 20 mm nominal size stone aggregate — is derived from 10 priced inputs for 10 sqm and works out to ₹614.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.2671,425.00380.48
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.0891,400.00124.60
0982Coarse sand (zone III)Materialcum0.1781,450.00258.10
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.175,156.00876.52
0124Mason 2nd classMason 2nd classLabourday0.8816.00652.80
0114BeldarLabourday1.4736.001,030.40
0101BhistiLabourday1.04816.00848.64
0127Driver (for Road Roller, Concrete Mixer, Truck etc.)Driver for (Road roller, concrete mixer, Trucks etc.)Labourday0.03897.0026.91
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.03900.0027.00
9999SundriesMaterialL.S.40.432.2791.78
TOTAL
4,317.23
Add 1 % Water charges on “W”
43.17
TOTAL
4,360.40
Add GST on “X” (multiplying factor 0.2127)
927.46
TOTAL
5,287.86
Add 15% CPOH on “Y”
793.18
TOTAL
6,081.04
Add Cess @ 1% on “Z”
60.81
Cost of 10 sqm.
6,141.85
Cost of 1 sqm.
614.19
Say
614.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 756. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.