Dry brick on edge flooring in required pattern with bricks of class designation 7.5 on a bed of 12 mm mud mortar, including filling joints with Jamuna sand, with common burnt clay non modular bricks

Item number
11.2
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹792.05/ SQM
D-01/RATE ANALYSISITEM 11.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.2 (Dry brick on edge flooring in required pattern with bricks of class designation 7.5 on a bed of 12 mm mud mortar, including filling joints with Jamuna sand, with common burnt clay non modular bricks) is derived from 6 priced inputs for 10 sqm and works out to ₹792.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 11.2DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2602MATCommon burnt clay F.P.S. (non modular) bricks class designation 7.51000 Nos0.6454,724.003,046.98
0983MATFine sand (zone IV)cum0.15980.00147.00
SUBRate as per Item Number 3.18 of SH: MortarsRate as per item 3.18cum0.15940.55141.08
0124LABMason 2nd classMason 2nd classday0.9816.00734.40
0115LABCoolieday1.98736.001,457.28
0101LABBhistiday0.05816.0040.80
BUILD-UP TO RATE
TOTAL
5,567.54
Add 1 % Water charges on “W”
+55.68
TOTAL
5,623.22
Add GST on “X” (multiplying factor 0.2127)
+1,196.06
TOTAL
6,819.28
Add 15% CPOH on “Y”
+1,022.89
TOTAL
7,842.17
Add Cess @ 1% on “Z”
+78.42
Cost of 10 sqm.
7,920.59
Cost of 1 sqm.
792.06
SAY
₹792.05
D-02/SOURCEPRINTED PAGE 756
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
756

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 756. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.