Extra for making chequers of approved pattern on cement concrete floors, steps, landing, pavements etc

Item number
11.8
Analysis basis
10 sqm
Priced inputs
3
Derived rate
₹83.85/ SQM
D-01/RATE ANALYSISITEM 11.8

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.8 (Extra for making chequers of approved pattern on cement concrete floors, steps, landing, pavements etc) is derived from 3 priced inputs for 10 sqm and works out to ₹83.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 11.8DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0124LABMason 2nd classMason 2nd classday0.36816.00293.76
0114LABBeldarday0.36736.00264.96
9999MATChequered plate etc.L.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
589.41
Add 1 % Water charges on “W”
+5.89
TOTAL
595.30
Add GST on “X” (multiplying factor 0.2127)
+126.62
TOTAL
721.92
Add 15% CPOH on “Y”
+108.29
TOTAL
830.21
Add Cess @ 1% on “Z”
+8.30
Cost of 10 sqm.
838.51
Cost of 1 sqm.
83.85
SAY
₹83.85
D-02/SOURCEPRINTED PAGE 759
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
759

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 759. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.