CPWD Analysis of Rates · Flooring

Providing and laying 500x500x40 mm thick Turf paver (Turfpave XD) on 150 mm thick sub grade of compacted bed of 20 mm thick nominal size stone aggregate and base course and filling with 150 mm thick jamuna sand, including spreading, well ramming, consolidating and finishing smooth etc. all complete as per direction of Engineer-in-charge

Item number
11.45
Analysis basis
Details of cost for 10 sqm.
Priced inputs
9
Derived rate
1,708.10 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.45 Providing and laying 500x500x40 mm thick Turf paver (Turfpave XD) on 150 mm thick sub grade of compacted bed of 20 mm thick nominal size stone aggregate and base course and filling with 150 mm thick jamuna sand, including spreading, well ramming, consolidating and finishing smooth etc. all complete as per direction of Engineer-in-charge — is derived from 9 priced inputs for 10 sqm and works out to ₹1,708.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 1 x 10 x 0.15 = 1.5cum
  • Providing and filling Jamuna sand
  • Labour for laying of Turf pave
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum1.51,425.002,137.50
0114BeldarLabourday0.7736.00515.20
0115CoolieLabourday0.52736.00382.72
0101BhistiLabourday0.36816.00293.76
Rate as per Item No.2.27 of SH: EARTH WORKRate as per item 2.27Sub-analysiscum1.52,123.753,185.63
2708Truf Paver (500 x 500 x 40 mm)Materialsqm10514.005,140.00
0123Mason 1st classMason 1st classLabourday0.5897.00448.50
0114BeldarLabourday1736.00736.00
9999SundriesMaterialL.S.502.27113.50
TOTAL
12,952.81
Add 1 % Water charges on “W-A”
97.67
TOTAL
13,050.48
Add GST on “X-A” (multiplying factor 0.2127)
2,098.25
TOTAL
15,148.73
Add 15% CPOH on “Y-A”
1,794.47
TOTAL
16,943.20
Add Cess @ 1% on “Z-A”
137.58
Cost of 10 sqm.
17,080.78
Cost of 1 sqm.
1,708.08
Say
1,708.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 828. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.