Providing and laying 500x500x40 mm thick Turf paver (Turfpave XD) on 150 mm thick sub grade of compacted bed of 20 mm thick nominal size stone aggregate and base course and filling with 150 mm thick jamuna sand, including spreading, well ramming, consolidating and finishing smooth etc. all complete as per direction of Engineer-in-charge

Item number
11.45
Analysis basis
10 sqm
Priced inputs
9
Derived rate
₹1,708.10/ SQM
D-01/RATE ANALYSISITEM 11.45

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.45 (Providing and laying 500x500x40 mm thick Turf paver (Turfpave XD) on 150 mm thick sub grade of compacted bed of 20 mm thick nominal size stone aggregate and base course and filling with 150 mm thick jamuna sand, including spreading, well ramming, consolidating and finishing smooth etc. all complete as per direction of Engineer-in-charge) is derived from 9 priced inputs for 10 sqm and works out to ₹1,708.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1 x 10 x 0.15 = 1.5cum
  • Providing and filling Jamuna sand
  • Labour for laying of Turf pave
ANALYSIS OF RATES · ITEM 11.45DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum1.51,425.002,137.50
0114LABBeldarday0.7736.00515.20
0115LABCoolieday0.52736.00382.72
0101LABBhistiday0.36816.00293.76
SUBRate as per Item No.2.27 of SH: EARTH WORKRate as per item 2.27cum1.52,123.753,185.63
2708MATTruf Paver (500 x 500 x 40 mm)sqm10514.005,140.00
0123LABMason 1st classMason 1st classday0.5897.00448.50
0114LABBeldarday1736.00736.00
9999MATSundriesL.S.502.27113.50
BUILD-UP TO RATE
TOTAL
12,952.81
Add 1 % Water charges on “W-A”
+97.67
TOTAL
13,050.48
Add GST on “X-A” (multiplying factor 0.2127)
+2,098.25
TOTAL
15,148.73
Add 15% CPOH on “Y-A”
+1,794.47
TOTAL
16,943.20
Add Cess @ 1% on “Z-A”
+137.58
Cost of 10 sqm.
17,080.78
Cost of 1 sqm.
1,708.08
SAY
₹1,708.10
D-02/SOURCEPRINTED PAGE 828
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
828

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 828. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.