Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, in skirting, riser of steps, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joint with white cement & matching pigments etc. complete

Size of Tile 500x500 mm
Item number
11.46.1
Analysis basis
10 sqm
Priced inputs
8
Derived rate
₹1,593.90/ SQM
D-01/RATE ANALYSISITEM 11.46.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.46.1 (Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, in skirting, riser of steps, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joint with white cement & matching pigments etc. complete Size of Tile 500x500 mm) is derived from 8 priced inputs for 10 sqm and works out to ₹1,593.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Vitrified floor tiles 50 x 50 cm size = 10
  • sqm+
  • sqm
  • Total = 10.25 sqm
  • 12 mm thick Cement mortar 1 : 3 (1
  • cement : 3 coarse sand)
  • Cement slurry over bed @ 3.3 kg per
  • sqm
  • Add wastage & breakage @ 2.5% = 0.25
ANALYSIS OF RATES · ITEM 11.46.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8620MATVitrified floor tile 50x50 cmVitrified floor tile 50x50 cm conforming to IS 15622:2006 group (B1a)sqm10.25530.005,432.50
9977MATCarriage of tilesL.S.62.42.27141.65
SUBRate as per Item No.3.8 of SH:MortarsRate as per item 3.8cum0.144,881.95683.47
9999MATMortar for pointing in white cementL.S.36.42.2782.63
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.0335,156.00170.15
0123LABMason 1st classMason 1st classday2.5897.002,242.50
0115LABCoolieday2.5736.001,840.00
9988MATSundries including carriage of quick set polymer etcL.S.269.12.27610.86
BUILD-UP TO RATE
TOTAL
11,203.76
Add 1 % Water charges on “W”
+112.04
TOTAL
11,315.80
Add GST on “X” (multiplying factor 0.2127)
+2,406.87
TOTAL
13,722.67
Add 15% CPOH on “Y”
+2,058.40
TOTAL
15,781.07
Add Cess @ 1% on “Z”
+157.81
Cost of 10 sqm
15,938.88
Cost for 1 sqm
1,593.89
SAY
₹1,593.90
D-02/SOURCEPRINTED PAGE 829
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
829

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 829. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.