Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, in skirting, riser of steps, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joint with white cement & matching pigments etc. complete
- Item number
- 11.46.1
- Analysis basis
- 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹1,593.90/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.46.1 (Providing and laying Vitrified tiles in different sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, in skirting, riser of steps, over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joint with white cement & matching pigments etc. complete Size of Tile 500x500 mm) is derived from 8 priced inputs for 10 sqm and works out to ₹1,593.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Vitrified floor tiles 50 x 50 cm size = 10
- sqm+
- sqm
- Total = 10.25 sqm
- 12 mm thick Cement mortar 1 : 3 (1
- cement : 3 coarse sand)
- Cement slurry over bed @ 3.3 kg per
- sqm
- Add wastage & breakage @ 2.5% = 0.25
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8620 | MAT | Vitrified floor tile 50x50 cmVitrified floor tile 50x50 cm conforming to IS 15622:2006 group (B1a) | sqm | 10.25 | 530.00 | 5,432.50 |
| 9977 | MAT | Carriage of tiles | L.S. | 62.4 | 2.27 | 141.65 |
| SUB | Rate as per Item No.3.8 of SH:MortarsRate as per item 3.8 | cum | 0.14 | 4,881.95 | 683.47 | |
| 9999 | MAT | Mortar for pointing in white cement | L.S. | 36.4 | 2.27 | 82.63 |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.033 | 5,156.00 | 170.15 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 2.5 | 897.00 | 2,242.50 |
| 0115 | LAB | Coolie | day | 2.5 | 736.00 | 1,840.00 |
| 9988 | MAT | Sundries including carriage of quick set polymer etc | L.S. | 269.1 | 2.27 | 610.86 |
- TOTAL
- 11,203.76
- Add 1 % Water charges on “W”
- +112.04
- TOTAL
- 11,315.80
- Add GST on “X” (multiplying factor 0.2127)
- +2,406.87
- TOTAL
- 13,722.67
- Add 15% CPOH on “Y”
- +2,058.40
- TOTAL
- 15,781.07
- Add Cess @ 1% on “Z”
- +157.81
- Cost of 10 sqm
- 15,938.88
- Cost for 1 sqm
- 1,593.89
- SAY
- ₹1,593.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 829
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 829. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.