Crazy ceramic tile flooring, with under layer 12 mm thick cement mortar 1:4 (1 cement: 4 coarse sand), with joints not exceeding 5 mm, including filling the gaps with ordinary cement mixture & mixing with synthetic polyester fibre, triangular in shape having specific gravity of 1.34 to 1.40, cross section size ranging from 10 to 40 micron & length upto 6 mm , mixing fibre @ 125 grams per 50 kg of cement in cement mortar, including providing and mixing water proofing material in mortar @ 1 kg per 50 kg of cement, all complete as per direction of Engineer-in-charge

Item number
11.44
Analysis basis
10 sqm
Priced inputs
17
Derived rate
₹954.15/ SQM
D-01/RATE ANALYSISITEM 11.44

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.44 (Crazy ceramic tile flooring, with under layer 12 mm thick cement mortar 1:4 (1 cement: 4 coarse sand), with joints not exceeding 5 mm, including filling the gaps with ordinary cement mixture & mixing with synthetic polyester fibre, triangular in shape having specific gravity of 1.34 to 1.40, cross section size ranging from 10 to 40 micron & length upto 6 mm , mixing fibre @ 125 grams per 50 kg of cement in cement mortar, including providing and mixing water proofing material in mortar @ 1 kg per 50 kg of cement, all complete as per direction of Engineer-in-charge) is derived from 17 priced inputs for 10 sqm and works out to ₹954.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Under layer 12 mm thick Cement mortar
  • 1:4 (1 cement : 4 coarse sand).
  • Cement slurry for subgrade
  • Top layer with tile piece and gap filling
  • with cement motar:
  • Ceramic tile piece for crazy flooring
  • assuming 70% tile area and 30% of joint
  • filler/mixture. (7.00x0.010)=0.07
  • 0.872x0.07/0.051=1.20 qtl
  • Cement motar 1:4 for filling of crazy tile
  • :(300x0.01=0.03)
  • Synthetic polyster triangular
  • Water proofing compound
ANALYSIS OF RATES · ITEM 11.44DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.3.9 of SH:MortarRate as per item 3.9cum0.144,211.70589.64
0124LABMason 2nd classMason 2nd classday0.67816.00546.72
0114LABBeldarday0.75736.00552.00
0101LABBhistiday0.92816.00750.72
9999MATSundriesL.S.8.972.2720.36
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.045,156.00206.24
0114LABBeldarday0.5736.00368.00
2709MATCeremic Tiles Pieces for Crazy Flooringquintal1.2148.00177.60
9977MATCarriage of tilesL.S.62.42.27141.65
SUBRate as per Item No.3.9 of SH:MortarRate as per item 3.9cum0.034,211.70126.35
SUBRate as per Item No.4.18 of SH: CONCRETE WORKRate as per item 4.18cement1.3870.3597.08
SUBRate as per Item No.4.12 of SH:CONCRETE WORKRate as per item 4.12cement1.3818.1525.05
0123LABMason 1st classMason 1st classday1.2897.001,076.40
0114LABBeldarday1736.00736.00
0115LABCoolieday1736.00736.00
0101LABBhistiday0.54816.00440.64
9999MATSundriesL.S.67.252.27152.66
BUILD-UP TO RATE
TOTAL
6,743.11
Add 1 % Water charges on “W-A”
+66.21
TOTAL
6,809.32
Add GST on “X-A” (multiplying factor 0.2127)
+1,422.37
TOTAL
8,231.69
Add 15% CPOH on “Y-A”
+1,216.43
TOTAL
9,448.12
Add Cess @ 1% on “Z-A”
+93.26
Cost of 10 sqm.
9,541.38
Cost of 1 sqm.
954.14
SAY
₹954.15
D-02/SOURCEPRINTED PAGE 827
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
827

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 827. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.