Crazy ceramic tile flooring, with under layer 12 mm thick cement mortar 1:4 (1 cement: 4 coarse sand), with joints not exceeding 5 mm, including filling the gaps with ordinary cement mixture & mixing with synthetic polyester fibre, triangular in shape having specific gravity of 1.34 to 1.40, cross section size ranging from 10 to 40 micron & length upto 6 mm , mixing fibre @ 125 grams per 50 kg of cement in cement mortar, including providing and mixing water proofing material in mortar @ 1 kg per 50 kg of cement, all complete as per direction of Engineer-in-charge
- Item number
- 11.44
- Analysis basis
- 10 sqm
- Priced inputs
- 17
- Derived rate
- ₹954.15/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.44 (Crazy ceramic tile flooring, with under layer 12 mm thick cement mortar 1:4 (1 cement: 4 coarse sand), with joints not exceeding 5 mm, including filling the gaps with ordinary cement mixture & mixing with synthetic polyester fibre, triangular in shape having specific gravity of 1.34 to 1.40, cross section size ranging from 10 to 40 micron & length upto 6 mm , mixing fibre @ 125 grams per 50 kg of cement in cement mortar, including providing and mixing water proofing material in mortar @ 1 kg per 50 kg of cement, all complete as per direction of Engineer-in-charge) is derived from 17 priced inputs for 10 sqm and works out to ₹954.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Under layer 12 mm thick Cement mortar
- 1:4 (1 cement : 4 coarse sand).
- Cement slurry for subgrade
- Top layer with tile piece and gap filling
- with cement motar:
- Ceramic tile piece for crazy flooring
- assuming 70% tile area and 30% of joint
- filler/mixture. (7.00x0.010)=0.07
- 0.872x0.07/0.051=1.20 qtl
- Cement motar 1:4 for filling of crazy tile
- :(300x0.01=0.03)
- Synthetic polyster triangular
- Water proofing compound
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item No.3.9 of SH:MortarRate as per item 3.9 | cum | 0.14 | 4,211.70 | 589.64 | |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.67 | 816.00 | 546.72 |
| 0114 | LAB | Beldar | day | 0.75 | 736.00 | 552.00 |
| 0101 | LAB | Bhisti | day | 0.92 | 816.00 | 750.72 |
| 9999 | MAT | Sundries | L.S. | 8.97 | 2.27 | 20.36 |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.04 | 5,156.00 | 206.24 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 2709 | MAT | Ceremic Tiles Pieces for Crazy Flooring | quintal | 1.2 | 148.00 | 177.60 |
| 9977 | MAT | Carriage of tiles | L.S. | 62.4 | 2.27 | 141.65 |
| SUB | Rate as per Item No.3.9 of SH:MortarRate as per item 3.9 | cum | 0.03 | 4,211.70 | 126.35 | |
| SUB | Rate as per Item No.4.18 of SH: CONCRETE WORKRate as per item 4.18 | cement | 1.38 | 70.35 | 97.08 | |
| SUB | Rate as per Item No.4.12 of SH:CONCRETE WORKRate as per item 4.12 | cement | 1.38 | 18.15 | 25.05 | |
| 0123 | LAB | Mason 1st classMason 1st class | day | 1.2 | 897.00 | 1,076.40 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
| 0115 | LAB | Coolie | day | 1 | 736.00 | 736.00 |
| 0101 | LAB | Bhisti | day | 0.54 | 816.00 | 440.64 |
| 9999 | MAT | Sundries | L.S. | 67.25 | 2.27 | 152.66 |
- TOTAL
- 6,743.11
- Add 1 % Water charges on “W-A”
- +66.21
- TOTAL
- 6,809.32
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,422.37
- TOTAL
- 8,231.69
- Add 15% CPOH on “Y-A”
- +1,216.43
- TOTAL
- 9,448.12
- Add Cess @ 1% on “Z-A”
- +93.26
- Cost of 10 sqm.
- 9,541.38
- Cost of 1 sqm.
- 954.14
- SAY
- ₹954.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 827
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 827. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.