Fixing glazed/ Ceramic/ Vitrified floor tiles with cement based high polymer modified quickset tile adhesive (Water based) conforming to IS: 15477, in average 3mm thickness

Item number
11.43
Analysis basis
1 sqm
Priced inputs
5
Derived rate
₹753.25/ SQM
D-01/RATE ANALYSISITEM 11.43

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.43 (Fixing glazed/ Ceramic/ Vitrified floor tiles with cement based high polymer modified quickset tile adhesive (Water based) conforming to IS: 15477, in average 3mm thickness) is derived from 5 priced inputs for 1 sqm and works out to ₹753.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 11.43DETAILS OF COST FOR 1 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8731MATHigh polymer modified quickset tile adhesiveper kg510.0050.00
9999MATMortar for pointing in white cementL.S.40.432.2791.78
0123LABMason 1st classMason 1st classday0.2897.00179.40
0115LABCoolieday0.2736.00147.20
9988MATSundries i/c carriage of cement etc.L.S.26.912.2761.09
BUILD-UP TO RATE
TOTAL
529.47
Add 1 % Water charges on “W”
+5.29
TOTAL
534.76
Add GST on “X” (multiplying factor 0.2127)
+113.74
TOTAL
648.50
Add 15% CPOH on “Y”
+97.28
TOTAL
745.78
Add Cess @ 1% on “Z”
+7.46
Cost for 1 sqm
753.24
SAY
₹753.25
D-02/SOURCEPRINTED PAGE 827
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
827

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 827. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.