CPWD Analysis of Rates · Flooring

Providing and laying Vitrified tiles in floor in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid on 20 mm thick cement mortar Glazed Vitrified tiles Matt/Antiskid finish of size

Size of Tile 1200 x 1200 mm

Item number
11.41A.3.5
Analysis basis
Detail of cost for 10 sqm
Priced inputs
9
Derived rate
2,838.50 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.41A.3.5 Providing and laying Vitrified tiles in floor in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid on 20 mm thick cement mortar Glazed Vitrified tiles Matt/Antiskid finish of size Size of Tile 1200 x 1200 mm — is derived from 9 priced inputs for 10 sqm and works out to ₹2,838.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Glazed Vitrified tiles Matt/Antiskid finish
  • 60 x 60 cm size =10 sqm+ Add wastage
  • & breakage @2.5% =0.25 sqm. Total =
  • 10.25 sqm
  • 20 mm thick Cement mortar 1 : 4 (1
  • cement : 4 coarse sand)
  • Cement for slurry over bed @ 3.3 kg per
  • sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
2766Glazed Vitrified tiles Matt/Antiskid finish of size 120 x 120 cmMaterialsqm10.251,428.0014,637.00
9977Carriage of tilesMaterialL.S.62.42.27141.65
Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysisCum0.244,211.701,010.81
9999Mortar for pointing in white cementMaterialL.S.262.2759.02
0367Portland cementPortland Cement (OPC-43 Grade)Materialtonne0.0335,156.00170.15
9999For notch trowel,plier, wedge, clips of required thickness, leveling system and rubber mallet etcMaterialL.S.252.2756.75
0123Mason 1st classMason 1st classLabourday2897.001,794.00
0115CoolieLabourday2736.001,472.00
9988sundries including carriage of quick set polymer etcMaterialL.S.269.12.27610.86
TOTAL
19,952.24
Add 1% Water charges on “W”
199.52
TOTAL
20,151.76
Add GST on “X” (multiplying factor 0.2127)
4,286.28
TOTAL
24,438.04
Add 15% CPOH on “Y”
3,665.71
TOTAL
28,103.75
Add Cess @ 1% on “Z”
281.04
Cost of 10 sqm
28,384.79
Cost of 1sqm
2,838.48
Say
2,838.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 825. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.