Providing and laying Vitrified tiles in floor in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid on 20 mm thick cement mortar Glazed Vitrified tiles Matt/Antiskid finish of size

Size of Tile 800 x 1200 mm
Item number
11.41A.3.4
Analysis basis
10 sqm
Priced inputs
9
Derived rate
₹2,056.90/ SQM
D-01/RATE ANALYSISITEM 11.41A.3.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.41A.3.4 (Providing and laying Vitrified tiles in floor in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid on 20 mm thick cement mortar Glazed Vitrified tiles Matt/Antiskid finish of size Size of Tile 800 x 1200 mm) is derived from 9 priced inputs for 10 sqm and works out to ₹2,056.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Glazed Vitrified tiles Matt/Antiskid finish
  • 80 x 120 cm size =10 sqm+ Add wastage
  • & breakage @2.5% =0.25 sqm. Total =
  • 10.25 sqm
  • 20 mm thick Cement mortar 1 : 4 (1
  • cement : 4 coarse sand)
  • Cement for slurry over bed @ 3.3 kg per
  • sqm
ANALYSIS OF RATES · ITEM 11.41A.3.4DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2765MATGlazed Vitrified tiles Matt/Antiskid finish of size 80 x 120 cmsqm10.25892.009,143.00
9977MATCarriage of tilesL.S.62.42.27141.65
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.244,211.701,010.81
9999MATMortar for pointing in white cementL.S.262.2759.02
0367MATPortland cementPortland Cement (OPC-43 Grade)tonne0.0335,156.00170.15
9999MATFor notch trowel,plier, wedge, clips of required thickness, leveling system and rubber mallet etcL.S.252.2756.75
0123LABMason 1st classMason 1st classday2897.001,794.00
0115LABCoolieday2736.001,472.00
9988MATsundries including carriage of quick set polymer etcL.S.269.12.27610.86
BUILD-UP TO RATE
TOTAL
14,458.24
Add 1% Water charges on “W”
+144.58
TOTAL
14,602.82
Add GST on “X” (multiplying factor 0.2127)
+3,106.02
TOTAL
17,708.84
Add 15% CPOH on “Y”
+2,656.33
TOTAL
20,365.17
Add Cess @ 1% on “Z”
+203.65
Cost of 10 sqm
20,568.82
Cost of 1sqm
2,056.88
SAY
₹2,056.90
D-02/SOURCEPRINTED PAGE 825
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
825

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 825. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.