Providing and laying Vitrified tiles in floor in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid on 20 mm thick cement mortar Glazed Vitrified tiles Matt/Antiskid finish of size
- Item number
- 11.41A.3.4
- Analysis basis
- 10 sqm
- Priced inputs
- 9
- Derived rate
- ₹2,056.90/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.41A.3.4 (Providing and laying Vitrified tiles in floor in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid on 20 mm thick cement mortar Glazed Vitrified tiles Matt/Antiskid finish of size Size of Tile 800 x 1200 mm) is derived from 9 priced inputs for 10 sqm and works out to ₹2,056.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Glazed Vitrified tiles Matt/Antiskid finish
- 80 x 120 cm size =10 sqm+ Add wastage
- & breakage @2.5% =0.25 sqm. Total =
- 10.25 sqm
- 20 mm thick Cement mortar 1 : 4 (1
- cement : 4 coarse sand)
- Cement for slurry over bed @ 3.3 kg per
- sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2765 | MAT | Glazed Vitrified tiles Matt/Antiskid finish of size 80 x 120 cm | sqm | 10.25 | 892.00 | 9,143.00 |
| 9977 | MAT | Carriage of tiles | L.S. | 62.4 | 2.27 | 141.65 |
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.24 | 4,211.70 | 1,010.81 | |
| 9999 | MAT | Mortar for pointing in white cement | L.S. | 26 | 2.27 | 59.02 |
| 0367 | MAT | Portland cementPortland Cement (OPC-43 Grade) | tonne | 0.033 | 5,156.00 | 170.15 |
| 9999 | MAT | For notch trowel,plier, wedge, clips of required thickness, leveling system and rubber mallet etc | L.S. | 25 | 2.27 | 56.75 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 2 | 897.00 | 1,794.00 |
| 0115 | LAB | Coolie | day | 2 | 736.00 | 1,472.00 |
| 9988 | MAT | sundries including carriage of quick set polymer etc | L.S. | 269.1 | 2.27 | 610.86 |
- TOTAL
- 14,458.24
- Add 1% Water charges on “W”
- +144.58
- TOTAL
- 14,602.82
- Add GST on “X” (multiplying factor 0.2127)
- +3,106.02
- TOTAL
- 17,708.84
- Add 15% CPOH on “Y”
- +2,656.33
- TOTAL
- 20,365.17
- Add Cess @ 1% on “Z”
- +203.65
- Cost of 10 sqm
- 20,568.82
- Cost of 1sqm
- 2,056.88
- SAY
- ₹2,056.90
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 825
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 825. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.