38 mm thick wood block flooring of first class teak wood laid over 25 mm thick leveling layer of cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 10 mm nominal size) to be paid separately, coated with a thin layer of hot bitumen penetration 80/25 (blown type) @ 2.45 kg per sqm, including fixing blocks in position after dipping in hot bitumen (blown type) up to half depth, planed, levelled smooth and finished complete

Item number
11.34
Analysis basis
Details of cost for 10sqm.
Priced inputs
8
Derived rate
₹12,020.45
D-01/RATE ANALYSISITEM 11.34

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.34 (38 mm thick wood block flooring of first class teak wood laid over 25 mm thick leveling layer of cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 10 mm nominal size) to be paid separately, coated with a thin layer of hot bitumen penetration 80/25 (blown type) @ 2.45 kg per sqm, including fixing blocks in position after dipping in hot bitumen (blown type) up to half depth, planed, levelled smooth and finished complete) is derived from 8 priced inputs and works out to ₹12,020.45 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Bitumen blown type
  • i) For bed layer @ 2.45kg/sqm. =
  • 2.45kg+
  • ii) For dipping blocks L.S. = 2.00Kg.
  • Total for 10sqm = 10X4.45kg = 44.5 kg
ANALYSIS OF RATES · ITEM 11.34DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0313MATBlown type petroleum bitumen of penetration 85/25 of approved qualitytonne0.04438,250.001,683.00
1187MATFirst class teak wood in scantling10 cudm41.8880.0036,784.00
0111LABCarpenter 1st classday17.5897.0015,697.50
0114LABBeldarday22.5736.0016,560.00
0115LABCoolieday15736.0011,040.00
0130LABMistryday1897.00897.00
9999MATSundries such as fuel, kerosene oil,———
OTHERsand paper etc.L.S.807.32.271,832.57
BUILD-UP TO RATE
TOTAL
84,494.07
Add 1 % Water charges on “W”
+844.94
TOTAL
85,339.01
Add GST on “X” (multiplying factor 0.2127)
+18,151.61
TOTAL
1,03,490.62
Add 15% CPOH on “Y”
+15,523.59
TOTAL
1,19,014.21
Add Cess @ 1% on “Z”
+1,190.14
Cost for 10 sqm.
1,20,204.35
Cost for 1 sqm.
12,020.44
SAY
₹12,020.45
D-02/SOURCEPRINTED PAGE 806
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
806

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 806. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.