CPWD Analysis of Rates · Flooring
38 mm thick wood block flooring of first class teak wood laid over 25 mm thick leveling layer of cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 10 mm nominal size) to be paid separately, coated with a thin layer of hot bitumen penetration 80/25 (blown type) @ 2.45 kg per sqm, including fixing blocks in position after dipping in hot bitumen (blown type) up to half depth, planed, levelled smooth and finished complete
- Item number
- 11.34
- Analysis basis
- Details of cost for 10sqm.
- Priced inputs
- 8
- Derived rate
- ₹12,020.45
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.34 — 38 mm thick wood block flooring of first class teak wood laid over 25 mm thick leveling layer of cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 10 mm nominal size) to be paid separately, coated with a thin layer of hot bitumen penetration 80/25 (blown type) @ 2.45 kg per sqm, including fixing blocks in position after dipping in hot bitumen (blown type) up to half depth, planed, levelled smooth and finished complete — is derived from 8 priced inputs and works out to ₹12,020.45 after water charges, GST, CPOH and cess. The full build-up is below.
- Bitumen blown type
- i) For bed layer @ 2.45kg/sqm. =
- 2.45kg+
- ii) For dipping blocks L.S. = 2.00Kg.
- Total for 10sqm = 10X4.45kg = 44.5 kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0313 | Blown type petroleum bitumen of penetration 85/25 of approved qualityMaterial | tonne | 0.044 | 38,250.00 | 1,683.00 |
| 1187 | First class teak wood in scantlingMaterial | 10 cudm | 41.8 | 880.00 | 36,784.00 |
| 0111 | Carpenter 1st classLabour | day | 17.5 | 897.00 | 15,697.50 |
| 0114 | BeldarLabour | day | 22.5 | 736.00 | 16,560.00 |
| 0115 | CoolieLabour | day | 15 | 736.00 | 11,040.00 |
| 0130 | MistryLabour | day | 1 | 897.00 | 897.00 |
| 9999 | Sundries such as fuel, kerosene oil,Material | NaN | NaN | NaN | |
| sand paper etc.Other | L.S. | 807.3 | 2.27 | 1,832.57 |
- TOTAL
- 84,494.07
- Add 1 % Water charges on “W”
- 844.94
- TOTAL
- 85,339.01
- Add GST on “X” (multiplying factor 0.2127)
- 18,151.61
- TOTAL
- 1,03,490.62
- Add 15% CPOH on “Y”
- 15,523.59
- TOTAL
- 1,19,014.21
- Add Cess @ 1% on “Z”
- 1,190.14
- Cost for 10 sqm.
- 1,20,204.35
- Cost for 1 sqm.
- 12,020.44
- Say
- 12,020.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 806. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.