Providing and fixing M.S. angle 50x50x5 mm to act as nosing with lugs of M.S. flat 10x5 mm, 10 cm long, forked at end 60cm apart (minimum three lugs to be provided), including necessary welding and applying a priming coat of approved primer on exposed surface etc. complete
- Item number
- 11.35
- Analysis basis
- Details of cost for 30m =[(11.40+0.24kg )
- Priced inputs
- 8
- Derived rate
- ₹177.80
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.35 (Providing and fixing M.S. angle 50x50x5 mm to act as nosing with lugs of M.S. flat 10x5 mm, 10 cm long, forked at end 60cm apart (minimum three lugs to be provided), including necessary welding and applying a priming coat of approved primer on exposed surface etc. complete) is derived from 8 priced inputs and works out to ₹177.80 after water charges, GST, CPOH and cess. The full build-up is below.
- x10= 116.4kg]
- Angle iron 50x50x5 mm =30 m
- Total=31.5 m @ 3.80 kg per m =
- 119.7 kg Say 1.2 qtl
- Lugs 10x5 mm flat = 10x6x0.10 = 6 m@
- 0.40 kg per m = 2.4 kg
- 6cm (lugs)
- Priming coat 30x0.20 = 6 sqm
- Add wastage @ 5% = 1.5 m
- Add wastage @ 5% = 0.12 kg
- Total 2.52 kg or 0.025 qtl
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1007 | MAT | Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joists | quintal | 1.2 | 5,965.00 | 7,158.00 |
| 1008 | MAT | Flats upto 10 mm in thicknessFlats up to 10 mm in thickness | quintal | 0.025 | 5,450.00 | 136.25 |
| 1215 | MAT | Welding by electric plant | cm | 60 | 2.50 | 150.00 |
| 9999 | MAT | Sundries | L.S. | 91 | 2.27 | 206.57 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.9 | 816.00 | 734.40 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 4.5 | 897.00 | 4,036.50 |
| 0114 | LAB | Beldar | day | 2.5 | 736.00 | 1,840.00 |
| SUB | Rate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3 | sqm | 6 | 67.40 | 404.40 |
- TOTAL
- 14,666.12
- Add 1 % Water charges on “W-A”
- +142.62
- TOTAL
- 14,808.74
- Add GST on “X-A” (multiplying factor 0.2127)
- +3,063.80
- TOTAL
- 17,872.54
- Add 15% CPOH on “Y-A”
- +2,620.22
- TOTAL
- 20,492.76
- Add Cess @ 1% on “Z-A”
- +200.88
- Cost for 116.4 kg.
- 20,693.64
- Cost per 1 Kg.
- 177.78
- SAY
- ₹177.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 807
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 807. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.