Providing and fixing M.S. angle 50x50x5 mm to act as nosing with lugs of M.S. flat 10x5 mm, 10 cm long, forked at end 60cm apart (minimum three lugs to be provided), including necessary welding and applying a priming coat of approved primer on exposed surface etc. complete

Item number
11.35
Analysis basis
Details of cost for 30m =[(11.40+0.24kg )
Priced inputs
8
Derived rate
₹177.80
D-01/RATE ANALYSISITEM 11.35

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.35 (Providing and fixing M.S. angle 50x50x5 mm to act as nosing with lugs of M.S. flat 10x5 mm, 10 cm long, forked at end 60cm apart (minimum three lugs to be provided), including necessary welding and applying a priming coat of approved primer on exposed surface etc. complete) is derived from 8 priced inputs and works out to ₹177.80 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • x10= 116.4kg]
  • Angle iron 50x50x5 mm =30 m
  • Total=31.5 m @ 3.80 kg per m =
  • 119.7 kg Say 1.2 qtl
  • Lugs 10x5 mm flat = 10x6x0.10 = 6 m@
  • 0.40 kg per m = 2.4 kg
  • 6cm (lugs)
  • Priming coat 30x0.20 = 6 sqm
  • Add wastage @ 5% = 1.5 m
  • Add wastage @ 5% = 0.12 kg
  • Total 2.52 kg or 0.025 qtl
ANALYSIS OF RATES · ITEM 11.35DETAILS OF COST FOR 30M =[(11.40+0.24KG )
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1007MATStructurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsquintal1.25,965.007,158.00
1008MATFlats upto 10 mm in thicknessFlats up to 10 mm in thicknessquintal0.0255,450.00136.25
1215MATWelding by electric plantcm602.50150.00
9999MATSundriesL.S.912.27206.57
0103LABBlacksmith 2nd classday0.9816.00734.40
0123LABMason 1st classMason 1st classday4.5897.004,036.50
0114LABBeldarday2.5736.001,840.00
SUBRate as per item no 13.50.3 of SH : FinishingRate as per item 13.50.3sqm667.40404.40
BUILD-UP TO RATE
TOTAL
14,666.12
Add 1 % Water charges on “W-A”
+142.62
TOTAL
14,808.74
Add GST on “X-A” (multiplying factor 0.2127)
+3,063.80
TOTAL
17,872.54
Add 15% CPOH on “Y-A”
+2,620.22
TOTAL
20,492.76
Add Cess @ 1% on “Z-A”
+200.88
Cost for 116.4 kg.
20,693.64
Cost per 1 Kg.
177.78
SAY
₹177.80
D-02/SOURCEPRINTED PAGE 807
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
807

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 807. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.