CPWD Analysis of Rates · Flooring
25 mm wooden planking, tongued and grooved in flooring, including fixing with iron screws complete with
Second class deodar wood
- Item number
- 11.33.2
- Analysis basis
- Details of cost for 2.5x4=10 sqm.
- Priced inputs
- 6
- Derived rate
- ₹3,029.75
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.33.2 — 25 mm wooden planking, tongued and grooved in flooring, including fixing with iron screws complete with : Second class deodar wood — is derived from 6 priced inputs and works out to ₹3,029.75 after water charges, GST, CPOH and cess. The full build-up is below.
- Second class deodar wood planks
- No of joints = 4000/138 = 28.97
- Total = (29-1) = 28 nos
- Qty of wood required
- 2.5(4+0.336)x0.025 = 0.271 cum
- Total = 0.2981 cum = 298.1 cudm
- (slotted counters sunk head type)
- Add wastage @ 10 % = 0.027 cum
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1194 | Second class deodar wood in planksMaterial | 10 cudm | 29.81 | 500.00 | 14,905.00 |
| 2500 | Extra for selected planks of second class deodar woodMaterial | 10 cudm | 29.81 | 115.00 | 3,428.15 |
| 0682 | Oxidised mild steel screws 50 mmMaterial | 100 Nos | 2 | 85.00 | 170.00 |
| 0111 | Carpenter 1st classLabour | day | 2.16 | 897.00 | 1,937.52 |
| 0114 | BeldarLabour | day | 1.08 | 736.00 | 794.88 |
| 9999 | Sundries for glue etc.Material | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 21,296.64
- Add 1 % Water charges on “W”
- 212.97
- TOTAL
- 21,509.61
- Add GST on “X” (multiplying factor 0.2127)
- 4,575.09
- TOTAL
- 26,084.70
- Add 15% CPOH on “Y”
- 3,912.71
- TOTAL
- 29,997.41
- Add Cess @ 1% on “Z”
- 299.97
- Cost for 10 sqm.
- 30,297.38
- Cost for 1sqm.
- 3,029.74
- Say
- 3,029.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 806. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.