25 mm wooden planking, tongued and grooved in flooring, including fixing with iron screws complete with

Second class teak wood
Item number
11.33.1
Analysis basis
Details of cost for 2.5x4=10 sqm.
Priced inputs
6
Derived rate
₹4,508.95
D-01/RATE ANALYSISITEM 11.33.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.33.1 (25 mm wooden planking, tongued and grooved in flooring, including fixing with iron screws complete with : Second class teak wood) is derived from 6 priced inputs and works out to ₹4,508.95 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Second class indian teak wood
  • No of joints = 4000/138 = 28.97
  • Total = (29-1) = 28 nos
  • Qty of wood required
  • 2.5(4+0.336)x0.025 = 0.271 cum
  • Total = 0.2981 cum = 298.1 cudm
  • (slotted counters sunk head type)
  • Add wastage @ 10 % = 0.027 cum
ANALYSIS OF RATES · ITEM 11.33.1DETAILS OF COST FOR 2.5X4=10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1190MATSecond class teak wood in planks10 cudm29.81791.0023,579.71
1231MATExtra for selected planks of second class teakwood10 cudm29.81150.004,471.50
0682MATOxidised mild steel screws 50 mm100 Nos285.00170.00
0111LABCarpenter 1st classday2.68897.002,403.96
0114LABBeldarday1.35736.00993.60
9999MATSundries for glue etc.L.S.33.282.2775.55
BUILD-UP TO RATE
TOTAL
31,694.32
Add 1 % Water charges on “W”
+316.94
TOTAL
32,011.26
Add GST on “X” (multiplying factor 0.2127)
+6,808.80
TOTAL
38,820.06
Add 15% CPOH on “Y”
+5,823.01
TOTAL
44,643.07
Add Cess @ 1% on “Z”
+446.43
Cost for 10 sqm.
45,089.50
Cost for 1sqm.
4,508.95
SAY
₹4,508.95
D-02/SOURCEPRINTED PAGE 805
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
805

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 805. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.