CPWD Analysis of Rates · Flooring

25 mm wooden planking, tongued and grooved in flooring, including fixing with iron screws complete with

Second class teak wood

Item number
11.33.1
Analysis basis
Details of cost for 2.5x4=10 sqm.
Priced inputs
6
Derived rate
4,508.95

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.33.1 25 mm wooden planking, tongued and grooved in flooring, including fixing with iron screws complete with : Second class teak wood — is derived from 6 priced inputs and works out to ₹4,508.95 after water charges, GST, CPOH and cess. The full build-up is below.

  • Second class indian teak wood
  • No of joints = 4000/138 = 28.97
  • Total = (29-1) = 28 nos
  • Qty of wood required
  • 2.5(4+0.336)x0.025 = 0.271 cum
  • Total = 0.2981 cum = 298.1 cudm
  • (slotted counters sunk head type)
  • Add wastage @ 10 % = 0.027 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1190Second class teak wood in planksMaterial10 cudm29.81791.0023,579.71
1231Extra for selected planks of second class teakwoodMaterial10 cudm29.81150.004,471.50
0682Oxidised mild steel screws 50 mmMaterial100 Nos285.00170.00
0111Carpenter 1st classLabourday2.68897.002,403.96
0114BeldarLabourday1.35736.00993.60
9999Sundries for glue etc.MaterialL.S.33.282.2775.55
TOTAL
31,694.32
Add 1 % Water charges on “W”
316.94
TOTAL
32,011.26
Add GST on “X” (multiplying factor 0.2127)
6,808.80
TOTAL
38,820.06
Add 15% CPOH on “Y”
5,823.01
TOTAL
44,643.07
Add Cess @ 1% on “Z”
446.43
Cost for 10 sqm.
45,089.50
Cost for 1sqm.
4,508.95
Say
4,508.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 805. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works