CPWD Analysis of Rates · Flooring

Extra for Kota stone/ sand stone in treads of steps and risers using single length above normal size up to 2.00 metre

Item number
11.32
Analysis basis
Details of cost for 10sqm.
Priced inputs
2
Derived rate
44.15

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.32 Extra for Kota stone/ sand stone in treads of steps and risers using single length above normal size up to 2.00 metre — is derived from 2 priced inputs and works out to ₹44.15 after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0124Mason 2nd classMason 2nd classLabourday0.2816.00163.20
0114BeldarLabourday0.2736.00147.20
TOTAL
310.40
Add 1 % Water charges on “W”
3.10
TOTAL
313.50
Add GST on “X” (multiplying factor 0.2127)
66.68
TOTAL
380.18
Add 15% CPOH on “Y”
57.03
TOTAL
437.21
Add Cess @ 1% on “Z”
4.37
Cost for 10sqm.
441.58
Cost for 1sqm.
44.16
Say
44.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 805. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works