CPWD Analysis of Rates · Flooring
Extra for Kota stone/ sand stone in treads of steps and risers using single length above normal size up to 2.00 metre
- Item number
- 11.32
- Analysis basis
- Details of cost for 10sqm.
- Priced inputs
- 2
- Derived rate
- ₹44.15
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.32 — Extra for Kota stone/ sand stone in treads of steps and risers using single length above normal size up to 2.00 metre — is derived from 2 priced inputs and works out to ₹44.15 after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.2 | 816.00 | 163.20 |
| 0114 | BeldarLabour | day | 0.2 | 736.00 | 147.20 |
- TOTAL
- 310.40
- Add 1 % Water charges on “W”
- 3.10
- TOTAL
- 313.50
- Add GST on “X” (multiplying factor 0.2127)
- 66.68
- TOTAL
- 380.18
- Add 15% CPOH on “Y”
- 57.03
- TOTAL
- 437.21
- Add Cess @ 1% on “Z”
- 4.37
- Cost for 10sqm.
- 441.58
- Cost for 1sqm.
- 44.16
- Say
- 44.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 805. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works