Skip to main content
R/DAR 2023

Extra for pre finished nosing in treads of steps of Kota stone/ sand stone slab

Item number
11.31
Analysis basis
10 metre
Priced inputs
1
Derived rate
₹191.40/ METRE
D-01/RATE ANALYSISITEM 11.31

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.31 (Extra for pre finished nosing in treads of steps of Kota stone/ sand stone slab) is derived from 1 priced inputs for 10 metre and works out to ₹191.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 11.31DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0126LABMason (for ornamental stone work) 1st classday1.5897.001,345.50
BUILD-UP TO RATE
TOTAL
1,345.50
Add 1 % Water charges on “W”
+13.46
TOTAL
1,358.96
Add GST on “X” (multiplying factor 0.2127)
+289.05
TOTAL
1,648.01
Add 15% CPOH on “Y”
+247.20
TOTAL
1,895.21
Add Cess @ 1% on “Z”
+18.95
Cost for 10metre
1,914.16
Cost for 1 metre
191.42
SAY
₹191.40
D-02/SOURCEPRINTED PAGE 804
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
804

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 804. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.