CPWD Analysis of Rates · Flooring
Extra for pre finished nosing in treads of steps of Kota stone/ sand stone slab
- Item number
- 11.31
- Analysis basis
- Details of cost for 10 metre
- Priced inputs
- 1
- Derived rate
- ₹191.40 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.31 — Extra for pre finished nosing in treads of steps of Kota stone/ sand stone slab — is derived from 1 priced inputs for 10 metre and works out to ₹191.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0126 | Mason (for ornamental stone work) 1st classLabour | day | 1.5 | 897.00 | 1,345.50 |
- TOTAL
- 1,345.50
- Add 1 % Water charges on “W”
- 13.46
- TOTAL
- 1,358.96
- Add GST on “X” (multiplying factor 0.2127)
- 289.05
- TOTAL
- 1,648.01
- Add 15% CPOH on “Y”
- 247.20
- TOTAL
- 1,895.21
- Add Cess @ 1% on “Z”
- 18.95
- Cost for 10metre
- 1,914.16
- Cost for 1 metre
- 191.42
- Say
- 191.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 804. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works