40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar
- Item number
- 11.28.2
- Analysis basis
- Details of cost for 10sqm.
- Priced inputs
- 8
- Derived rate
- ₹1,342.65
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.28.2 (40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar White sand stone) is derived from 8 priced inputs and works out to ₹1,342.65 after water charges, GST, CPOH and cess. The full build-up is below.
- Finished work = 10 sqm
- Total = 11 sqm
- Cement mortar 1 : 5 (1 cement :
- 5 coarse sand)
- (i) for beading = 0.224 cum+
- (ii) for joining = 0.026 cum.
- Total=0.250cum.
- Add for wastage @ 10% = 1 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1165 | MAT | White sand stone slab 40 mm thick (undressed)White sand stone slab 40 mm thick (un-dressed) | sqm | 11 | 370.00 | 4,070.00 |
| 9977 | MAT | Carriage | L.S. | 34.06 | 2.27 | 77.32 |
| SUB | Rate as per Item Number 3.10 of SH: MortarsRate as per item 3.10 | cum | 0.25 | 3,850.75 | 962.69 | |
| 0123 | LAB | Mason 1st classMason 1st class | day | 3.1 | 897.00 | 2,780.70 |
| 0100 | LAB | Bandhani | day | 1.1 | 816.00 | 897.60 |
| 0115 | LAB | Coolie | day | 0.55 | 736.00 | 404.80 |
| 0101 | LAB | Bhisti | day | 0.27 | 816.00 | 220.32 |
| 9999 | MAT | Sundries | L.S. | 10.79 | 2.27 | 24.49 |
- TOTAL
- 9,437.92
- Add 1 % Water charges on “W”
- +94.38
- TOTAL
- 9,532.30
- Add GST on “X” (multiplying factor 0.2127)
- +2,027.52
- TOTAL
- 11,559.82
- Add 15% CPOH on “Y”
- +1,733.97
- TOTAL
- 13,293.79
- Add Cess @ 1% on “Z”
- +132.94
- Cost for 10sqm.
- 13,426.73
- Cost for 1sqm.
- 1,342.67
- SAY
- ₹1,342.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 800
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 800. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.