CPWD Analysis of Rates · Flooring
40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar
White sand stone
- Item number
- 11.28.2
- Analysis basis
- Details of cost for 10sqm.
- Priced inputs
- 8
- Derived rate
- ₹1,342.65
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.28.2 — 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar White sand stone — is derived from 8 priced inputs and works out to ₹1,342.65 after water charges, GST, CPOH and cess. The full build-up is below.
- Finished work = 10 sqm
- Total = 11 sqm
- Cement mortar 1 : 5 (1 cement :
- 5 coarse sand)
- (i) for beading = 0.224 cum+
- (ii) for joining = 0.026 cum.
- Total=0.250cum.
- Add for wastage @ 10% = 1 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1165 | White sand stone slab 40 mm thick (undressed)White sand stone slab 40 mm thick (un-dressed)Material | sqm | 11 | 370.00 | 4,070.00 |
| 9977 | CarriageMaterial | L.S. | 34.06 | 2.27 | 77.32 |
| Rate as per Item Number 3.10 of SH: MortarsRate as per item 3.10Sub-analysis | cum | 0.25 | 3,850.75 | 962.69 | |
| 0123 | Mason 1st classMason 1st classLabour | day | 3.1 | 897.00 | 2,780.70 |
| 0100 | BandhaniLabour | day | 1.1 | 816.00 | 897.60 |
| 0115 | CoolieLabour | day | 0.55 | 736.00 | 404.80 |
| 0101 | BhistiLabour | day | 0.27 | 816.00 | 220.32 |
| 9999 | SundriesMaterial | L.S. | 10.79 | 2.27 | 24.49 |
- TOTAL
- 9,437.92
- Add 1 % Water charges on “W”
- 94.38
- TOTAL
- 9,532.30
- Add GST on “X” (multiplying factor 0.2127)
- 2,027.52
- TOTAL
- 11,559.82
- Add 15% CPOH on “Y”
- 1,733.97
- TOTAL
- 13,293.79
- Add Cess @ 1% on “Z”
- 132.94
- Cost for 10sqm.
- 13,426.73
- Cost for 1sqm.
- 1,342.67
- Say
- 1,342.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 800. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.