Skip to main content
R/DAR 2023

40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar

White sand stone
Item number
11.28.2
Analysis basis
Details of cost for 10sqm.
Priced inputs
8
Derived rate
₹1,342.65
D-01/RATE ANALYSISITEM 11.28.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.28.2 (40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar White sand stone) is derived from 8 priced inputs and works out to ₹1,342.65 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Finished work = 10 sqm
  • Total = 11 sqm
  • Cement mortar 1 : 5 (1 cement :
  • 5 coarse sand)
  • (i) for beading = 0.224 cum+
  • (ii) for joining = 0.026 cum.
  • Total=0.250cum.
  • Add for wastage @ 10% = 1 sqm
ANALYSIS OF RATES · ITEM 11.28.2DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1165MATWhite sand stone slab 40 mm thick (undressed)White sand stone slab 40 mm thick (un-dressed)sqm11370.004,070.00
9977MATCarriageL.S.34.062.2777.32
SUBRate as per Item Number 3.10 of SH: MortarsRate as per item 3.10cum0.253,850.75962.69
0123LABMason 1st classMason 1st classday3.1897.002,780.70
0100LABBandhaniday1.1816.00897.60
0115LABCoolieday0.55736.00404.80
0101LABBhistiday0.27816.00220.32
9999MATSundriesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
9,437.92
Add 1 % Water charges on “W”
+94.38
TOTAL
9,532.30
Add GST on “X” (multiplying factor 0.2127)
+2,027.52
TOTAL
11,559.82
Add 15% CPOH on “Y”
+1,733.97
TOTAL
13,293.79
Add Cess @ 1% on “Z”
+132.94
Cost for 10sqm.
13,426.73
Cost for 1sqm.
1,342.67
SAY
₹1,342.65
D-02/SOURCEPRINTED PAGE 800
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
800

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 800. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.