40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar

1:5 (1 cement : 5 coarse sand) with joints finished flush. Red sand stone
Item number
11.28.1
Analysis basis
Details of cost for 10sqm.
Priced inputs
8
Derived rate
₹1,280.10
D-01/RATE ANALYSISITEM 11.28.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.28.1 (40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar 1:5 (1 cement : 5 coarse sand) with joints finished flush. Red sand stone) is derived from 8 priced inputs and works out to ₹1,280.10 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Finished work = 10 sqm
  • Total = 11 sqm
  • Cement mortar 1 : 5 (1 cement : 5 coarse
  • sand)
  • (i) for beading = 0.224 cum+
  • (ii) for joining = 0.026 cum.
  • Total=0.250cum.
  • Add for wastage @ 10% = 1 sqm
ANALYSIS OF RATES · ITEM 11.28.1DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1164MATRed sand stone slab 40 mmthick (undressed)Red sand stone slab 40 mm thick (un-dressed)sqm11330.003,630.00
9977MATCarriageL.S.34.062.2777.32
SUBRate as per Item Number 3.10 of SH: MortarsRate as per item 3.10cum0.253,850.75962.69
0123LABMason 1st classMason 1st classday3.1897.002,780.70
0100LABBandhaniday1.1816.00897.60
0115LABCoolieday0.55736.00404.80
0101LABBhistiday0.27816.00220.32
9999MATSundriesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
8,997.92
Add 1 % Water charges on “W”
+89.98
TOTAL
9,087.90
Add GST on “X” (multiplying factor 0.2127)
+1,933.00
TOTAL
11,020.90
Add 15% CPOH on “Y”
+1,653.14
TOTAL
12,674.04
Add Cess @ 1% on “Z”
+126.74
Cost for 10sqm.
12,800.78
Cost for 1sqm.
1,280.08
SAY
₹1,280.10
D-02/SOURCEPRINTED PAGE 799
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
799

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 799. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.