CPWD Analysis of Rates · Flooring

Kota stone slabs 20 mm thick in risers of steps, skirting, dado and pillars laid on 12 mm (average) thick cement mortar 1:3 (1 cement: 3 coarse sand) and jointed with grey cement slurry mixed with pigment to match the shade of the slabs, including rubbing and polishing complete

Item number
11.27
Analysis basis
Details of cost for 10sqm.
Priced inputs
9
Derived rate
2,354.70

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.27 Kota stone slabs 20 mm thick in risers of steps, skirting, dado and pillars laid on 12 mm (average) thick cement mortar 1:3 (1 cement: 3 coarse sand) and jointed with grey cement slurry mixed with pigment to match the shade of the slabs, including rubbing and polishing complete — is derived from 9 priced inputs and works out to ₹2,354.70 after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
  • for slurry
CodeInputUnitQuantityRate (INR)Amount (INR)
1168Kota stone slab 20 mm to 25 mm thick (semi-polished) including 15% wastageKota stone slab 20 mm to 25 mm thick (semi-polished)Materialsqm11.5320.003,680.00
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.1444,881.95703.00
0367Portland CementPortland Cement (OPC-43 Grade)Materialtonne0.0645,156.00329.98
0874Black colour dark shade pigmentMaterialkilogram4.575.00337.50
0124Mason 2nd classMason 2nd classLabourday3816.002,448.00
0114BeldarLabourday3736.002,208.00
0115CoolieLabourday1736.00736.00
0139Skilled Beldar (for floor rubbing etc.)Labourday7816.005,712.00
9999SundriesMaterialL.S.174.982.27397.20
TOTAL
16,551.68
Add 1 % Water charges on “W”
165.52
TOTAL
16,717.20
Add GST on “X” (multiplying factor 0.2127)
3,555.75
TOTAL
20,272.95
Add 15% CPOH on “Y”
3,040.94
TOTAL
23,313.89
Add Cess @ 1% on “Z”
233.14
Cost for 10sqm.
23,547.03
Cost for 1sqm.
2,354.70
Say
2,354.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 799. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.