R/DAR 2023

Kota stone slabs 20 mm thick in risers of steps, skirting, dado and pillars laid on 12 mm (average) thick cement mortar 1:3 (1 cement: 3 coarse sand) and jointed with grey cement slurry mixed with pigment to match the shade of the slabs, including rubbing and polishing complete

Item number
11.27
Analysis basis
Details of cost for 10sqm.
Priced inputs
9
Derived rate
₹2,354.70
D-01/RATE ANALYSISITEM 11.27

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.27 (Kota stone slabs 20 mm thick in risers of steps, skirting, dado and pillars laid on 12 mm (average) thick cement mortar 1:3 (1 cement: 3 coarse sand) and jointed with grey cement slurry mixed with pigment to match the shade of the slabs, including rubbing and polishing complete) is derived from 9 priced inputs and works out to ₹2,354.70 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
  • for slurry
ANALYSIS OF RATES · ITEM 11.27DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1168MATKota stone slab 20 mm to 25 mm thick (semi-polished) including 15% wastageKota stone slab 20 mm to 25 mm thick (semi-polished)sqm11.5320.003,680.00
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum0.1444,881.95703.00
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.0645,156.00329.98
0874MATBlack colour dark shade pigmentkilogram4.575.00337.50
0124LABMason 2nd classMason 2nd classday3816.002,448.00
0114LABBeldarday3736.002,208.00
0115LABCoolieday1736.00736.00
0139LABSkilled Beldar (for floor rubbing etc.)day7816.005,712.00
9999MATSundriesL.S.174.982.27397.20
BUILD-UP TO RATE
TOTAL
16,551.68
Add 1 % Water charges on “W”
+165.52
TOTAL
16,717.20
Add GST on “X” (multiplying factor 0.2127)
+3,555.75
TOTAL
20,272.95
Add 15% CPOH on “Y”
+3,040.94
TOTAL
23,313.89
Add Cess @ 1% on “Z”
+233.14
Cost for 10sqm.
23,547.03
Cost for 1sqm.
2,354.70
SAY
₹2,354.70
D-02/SOURCEPRINTED PAGE 799
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
799

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 799. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.