Skip to main content
R/DAR 2023

Kota stone slab flooring over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab, including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand)

25 mm thick
Item number
11.26.1
Analysis basis
Details of cost for 10sqm.
Priced inputs
10
Derived rate
₹1,948.25
D-01/RATE ANALYSISITEM 11.26.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.26.1 (Kota stone slab flooring over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab, including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) : 25 mm thick) is derived from 10 priced inputs and works out to ₹1,948.25 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Cement for slurry-(i) for bedding = 44kg+
  • (ii) for joints = 20 kg.Total = 64 kg. or
  • 0.064 tonne
ANALYSIS OF RATES · ITEM 11.26.1DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1168MATKota stone slab 20 mm to 25 mm thick (semi-polished) including 15% wastageKota stone slab 20 mm to 25 mm thick (semi-polished)sqm11.5320.003,680.00
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.2244,211.70943.42
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.0645,156.00329.98
0874MATBlack colour dark shade pigmentkilogram4.575.00337.50
0124LABMason 2nd classMason 2nd classday1.2816.00979.20
0114LABBeldarday1736.00736.00
0115LABCoolieday1736.00736.00
0139LABSkilled Beldar (for floor rubbing etc.)day5816.004,080.00
0013MACHMachine for rubbing of floorsday4350.001,400.00
9999MATSundriesL.S.208.132.27472.46
BUILD-UP TO RATE
TOTAL
13,694.56
Add 1 % Water charges on “W”
+136.95
TOTAL
13,831.51
Add GST on “X” (multiplying factor 0.2127)
+2,941.96
TOTAL
16,773.47
Add 15% CPOH on “Y”
+2,516.02
TOTAL
19,289.49
Add Cess @ 1% on “Z”
+192.89
Cost for 10sqm.
19,482.38
Cost for 1sqm.
1,948.24
SAY
₹1,948.25
D-02/SOURCEPRINTED PAGE 798
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
798

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 798. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.