Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete, on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand)

Light shade pigment using white cement
Item number
11.20.1
Analysis basis
10 sqm
Priced inputs
9
Derived rate
₹1,402.00/ SQM
D-01/RATE ANALYSISITEM 11.20.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 11.20.1 (Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete, on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand) Light shade pigment using white cement) is derived from 9 priced inputs for 10 sqm and works out to ₹1,402.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement mortar 1 : 4 (1 cement : 4 coarse
  • sand)
  • Grey cement slury @ 4.4kg @sqm
  • White cement for grouting
ANALYSIS OF RATES · ITEM 11.20.1DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7070MATChequered precast cement concrete tiles 22mm thick using marble chips of size 6mm - Light shade using white cement including 10% wastageChequered precast cement concrete tiles 22 mm thick using marble chips of size 6 mm - Light shade using white cementsqm11392.004,312.00
9977MATCarriage of tilesL.S.40.432.2791.78
SUBRate as per Item Number 3.9 of SH: MortarsRate as per item 3.9cum0.224,211.70926.57
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.0445,156.00226.86
0368MATWhite Cementtonne0.04810,500.00504.00
0875MATRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentRed, chocolate, orange, buff or yellow (red oxide of iron) light shade pigmentkilogram3.0865.00200.20
0124LABMason 2nd classMason 2nd classday1.6816.001,305.60
0115LABCoolieday2736.001,472.00
0101LABBhistiday1816.00816.00
BUILD-UP TO RATE
TOTAL
9,855.01
Add 1 % Water charges on “W”
+98.55
TOTAL
9,953.56
Add GST on “X” (multiplying factor 0.2127)
+2,117.12
TOTAL
12,070.68
Add 15% CPOH on “Y”
+1,810.60
TOTAL
13,881.28
Add Cess @ 1% on “Z”
+138.81
Cost of 10 sqm.
14,020.09
Cost of 1 sqm.
1,402.01
SAY
₹1,402.00
D-02/SOURCEPRINTED PAGE 787
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
787

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 787. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFLOORING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.